Closeout of IE Bulletin 80-12: decay heat removal system operability

Technical Report ·
OSTI ID:5625184
On April 19, 1980, decay heat removal (DHR) capability was lost at Davis-Besse 1 for approximately two and one-half hours in a refueling mode. Typically for that mode, many systems and components were out of service for maintanance and testing or were deactivated to preclude inadvertent actuation. IE Bulletin 80-12 was issued May 9, 1980 for action by licensees of operating pressurized water reactors (PWRs); it was issued for information to nuclear power facilities other than operating PWRs. The intent of the bulletin ws to improve nuclear plant safety by reducing the likelihood of losing DHR capability in PWRs, especially when some DHR components are unavailable because of maintenance activities during refueling and cold shutdown modes of operation. A related NRR Generic Letter was issued June 11, 1980 to licensees of operating PWRs, requesting amendment of technical specifications to ensure long-term maintenance of DHR capability. Evaluation of utility responses and NRC/IE inspection reports indicates that the bulletin can be closed out per specific criteria for 33 (75%) of the 44 affected facilities.
Research Organization:
Parameter, Inc., Elm Grove, WI (USA)
OSTI ID:
5625184
Report Number(s):
NUREG/CR-4005; ON: TI85901679
Country of Publication:
United States
Language:
English