Title: DIII-D electron cyclotron heating 2 MW upgrade project. Final report, FY1989--FY1997

Technical Report ·
DOI:https://doi.org/10.2172/560863· OSTI ID:560863

The 2 MW, 110 GHz ECH system was based on the General Atomics Proposal to the Department of Energy: DIII-D Fusion Research Program Vol. I Technical, and Vol. II Cost (GACP-72-166, July 1987 and revised). This proposal was reviewed in August 1987 by a senior technical review committee, who recommended to vigorously pursue increasing the ECH power to 6 MW. The realization of the higher frequency and power ECH on DIII-D was recognized by the committee to be important, not only for the DIII-D program, but also for future devices and the whole ECH area. Subsequently, an engineering cost and schedule review was conducted by DOE-OAK which confirmed the GA costs and schedules and recommended proceeding directly to 10 MW. However, because of budgetary constraints, in the April 1988 Field Task Proposal submission, GA proposed a phased ECH approach, Phase I being 2 MW and Phase II increasing the power to 10 MW. After review, DOE instructed GA to initiate the prototype 2 MW, 110 GHz program. The contract to procure four 500 kW, 110 GHz, 10 s gyrotrons from Varian Associates was initiated in April 1989 with final delivery by November 1990. Because of difficulties in spreading the energy of the electron beam over the collector area, the testing of the first gyrotron delayed its delivery until February 1991. The second gyrotron was able to operate for 1 s at 500 kW and 2 s at 300 kW, but failed when the cavity suffered thermal damage.

Research Organization:
General Atomics International Services Corp., San Diego, CA (United States)
Sponsoring Organization:
USDOE Office of Energy Research, Washington, DC (United States)
DOE Contract Number:
AC03-89ER51114
OSTI ID:
560863
Report Number(s):
GA-C22680; ON: DE98001520; TRN: 98:008954
Resource Relation:
Other Information: PBD: Aug 1997
Country of Publication:
United States
Language:
English

Similar Records

Status of the DIII-D 110 GHz ECH system
Journal Article · Tue Dec 31 00:00:00 EST 1996 · Fusion Technology · OSTI ID:560863

Status of the DIII-D 110 GHz ECH system
Conference · Sat Jun 01 00:00:00 EDT 1996 · OSTI ID:560863

THE MEASURED PERFORMANCE OF A MILLIMETER WAVE BEAM SPLITTER
Conference · Sun Sep 01 00:00:00 EDT 2002 · OSTI ID:560863