Effect of resolution of the Millstone Point Unit 1 Systematic Evaluation Program issues on probabilistic calculations of risk
Technical Report
·
OSTI ID:5312791
The US NRC Systematic Evaluation Program (SEP) identifies deviations from current licensing requirements for older nuclear power plants. The Millstone Point Unit 1 (Millstone-1) plant is the first plant in the SEP which has had a probabilistic risk assessment (PRA) performed on it (as part of the Interim Reliability Evaluation Program, IREP). Sandia was requested to calculate the effect on risk of resolving the deviations identified by the SEP for Millstone-1. The results of the IREP Millstone-1 PRA were recalculated incorporating resolution of the issues which were within the scope of the original PRA. Of the 19 issues analyzed in detail, we calculated no reduction in core melt frequency, exposure, and risk for 12 issues, less than 2% reduction for 5 issues, and approx. 15% reduction for 2 interrelated issues if implemented together. These numbers should be viewed in the context of the very large uncertainties in PRA methodology and data. No attempt at cost/benefit analysis was made. The deviations not analyzed were generally those concerning the plant's response to external events such as flooding and earthquakes.
- Research Organization:
- Sandia National Labs., Albuquerque, NM (USA); Science Applications, Inc., Albuquerque, NM (USA)
- DOE Contract Number:
- AC04-76DP00789
- OSTI ID:
- 5312791
- Report Number(s):
- NUREG/CR-3233; SAND-82-2429; ON: DE84004666
- Country of Publication:
- United States
- Language:
- English
Similar Records
Interim reliability-evaluation program: analysis of the Millstone Point Unit 1 nuclear power plant. Volume I. Main report
Importance of data and related uncertainties in probabilistic risk assessments. [PWR; BWR]
Review and analysis of insights from plant transients gained from the Interim Reliability Evaluation Program
Technical Report
·
Fri Dec 31 23:00:00 EST 1982
·
OSTI ID:6345027
Importance of data and related uncertainties in probabilistic risk assessments. [PWR; BWR]
Conference
·
Mon Dec 31 23:00:00 EST 1984
·
OSTI ID:5950733
Review and analysis of insights from plant transients gained from the Interim Reliability Evaluation Program
Conference
·
Fri Dec 31 23:00:00 EST 1982
·
OSTI ID:5492151
Related Subjects
21 SPECIFIC NUCLEAR REACTORS AND ASSOCIATED PLANTS
210100 -- Power Reactors
Nonbreeding
Light-Water Moderated
Boiling Water Cooled
210700 -- Nuclear Power Plants-- Regulation & Licensing
22 GENERAL STUDIES OF NUCLEAR REACTORS
220900* -- Nuclear Reactor Technology-- Reactor Safety
ACCIDENTS
BWR TYPE REACTORS
ENRICHED URANIUM REACTORS
MELTDOWN
MILLSTONE-1 REACTOR
POWER REACTORS
PROBABILITY
REACTOR ACCIDENTS
REACTORS
RISK ASSESSMENT
WATER COOLED REACTORS
WATER MODERATED REACTORS
210100 -- Power Reactors
Nonbreeding
Light-Water Moderated
Boiling Water Cooled
210700 -- Nuclear Power Plants-- Regulation & Licensing
22 GENERAL STUDIES OF NUCLEAR REACTORS
220900* -- Nuclear Reactor Technology-- Reactor Safety
ACCIDENTS
BWR TYPE REACTORS
ENRICHED URANIUM REACTORS
MELTDOWN
MILLSTONE-1 REACTOR
POWER REACTORS
PROBABILITY
REACTOR ACCIDENTS
REACTORS
RISK ASSESSMENT
WATER COOLED REACTORS
WATER MODERATED REACTORS