Engineer, design, construct, test and evaluate a pressurized fluidized bed pilot plant using high sulfur coal for production of electric power. Phase III. Pilot plant construction. Quarterly report for the period September 1-November 30, 1981
Progress in the design, construction, testing and evaluation of a pressurized fluidized bed pilot plant is reported. The initial layout of the main control panel arrangement was completed. Refinements to the front panel equipment arrangement and designation of cable penetration locations are in progress. Parts and materials have been specified and are being procured. Engineering design of the process piping has been completed and fabrication is awaiting FY 82 funding. The replacement ASTM A105 material flanges for the air exchange housing have been successfully welded to the stainless steel 409 housings. Fabrication of the air exchange housing is continuing on schedule. Heat exchange tube fabrication at Curtiss-Wright continues on schedule. A significant quantity of the material handling equipment has been received at site with the remainder scheduled for delivery in December/January. Initial review of the hot gas cleanup collector design drawings has been completed.
- Research Organization:
- Curtiss-Wright Corp., Wood-Ridge, NJ (USA)
- DOE Contract Number:
- AC21-76ET10417
- OSTI ID:
- 5280132
- Report Number(s):
- DOE/ET/10417-1215; ON: DE82016391
- Resource Relation:
- Other Information: Portions of document are illegible
- Country of Publication:
- United States
- Language:
- English
Similar Records
Engineer, design, construct, test and evaluate a pressurized fluidized bed pilot plant using high sulfur coal for production of electric power. Phase I: preliminary engineering. Quarterly report, September 1-November 30, 1977
Engineer, design, construct, test and evaluate a pressurized fluidized bed pilot plant using high sulfur coal for production of electric power. Phase I. Preliminary engineering. Topical report, 1 March 1976-1 June 1977
Related Subjects
42 ENGINEERING
COMBINED-CYCLE POWER PLANTS
FLUIDIZED-BED COMBUSTORS
DEMONSTRATION PROGRAMS
PERFORMANCE TESTING
AIR POLLUTION CONTROL
COAL
DESIGN
FABRICATION
FOSSIL-FUEL POWER PLANTS
HEAT EXCHANGERS
HOT GAS CLEANUP
PILOT PLANTS
CARBONACEOUS MATERIALS
COMBUSTORS
CONTROL
ENERGY SOURCES
FOSSIL FUELS
FUELS
FUNCTIONAL MODELS
MATERIALS
POLLUTION CONTROL
POWER PLANTS
PURIFICATION
TESTING
THERMAL POWER PLANTS
200102* - Fossil-Fueled Power Plants- Power Cycles
421000 - Engineering- Combustion Systems