Engineer, design, construct, test and evaluate a pressurized fluidized bed pilot plant using high sulfur coal for production of electric power: Phase III. Pilot plant construction. Quarterly report, September 1-November 30, 1980
Technical Report
·
OSTI ID:5242024
Technical progress during the period September 1-November 30, 1980 on DOE Contract DE-AC21-76ET10417 is described. The design of the material handling equipment by the various vendors continues on schedule. Coal and dolomite feed system procurement was initiated. The SWEC Field Construction Office was established and site mobilization of the contractor for Bid Package No. 1 (Substructure) was initiated. Purchase orders were placed for the fabrication of all the PFB process recycle loop components. All preparatory work for placement of Bid Package No. 2, Structural Steel Erection, has been completed. Contract funding limitations have prevented placement of this purchase order.
- Research Organization:
- Curtiss-Wright Corp., Wood-Ridge, NJ (USA). Power Systems Div.
- DOE Contract Number:
- AC21-76ET10417
- OSTI ID:
- 5242024
- Report Number(s):
- CW-WR-76-015.57A; FE-1726-57A; ON: DE82004269
- Country of Publication:
- United States
- Language:
- English
Similar Records
Engineer, design, construct, test, and evaluate a pressurized fluidized-bed pilot plant using high-sulfur coal for production of electric power. Phase III: pilot-plant construction. Quarterly report, June 1-August 31, 1980
Engineeer, design, construct, test, and evaluate a pressurized fluidized-bed pilot plant using high-sulfur coal for production of electric power. Phase III: pilot plant construction. Quarterly report, March 1-May 31, 1980
Engineer, design, construction, test and evaluate a pressurized fluidized bed pilot plant using high sulfur coal for production of electric power. Phase III. Pilot plant construction. Quarterly report, June 1-August 31, 1981
Technical Report
·
Tue Jan 01 00:00:00 EST 1980
·
OSTI ID:5242024
Engineeer, design, construct, test, and evaluate a pressurized fluidized-bed pilot plant using high-sulfur coal for production of electric power. Phase III: pilot plant construction. Quarterly report, March 1-May 31, 1980
Technical Report
·
Tue Jan 01 00:00:00 EST 1980
·
OSTI ID:5242024
Engineer, design, construction, test and evaluate a pressurized fluidized bed pilot plant using high sulfur coal for production of electric power. Phase III. Pilot plant construction. Quarterly report, June 1-August 31, 1981
Technical Report
·
Thu Jan 01 00:00:00 EST 1981
·
OSTI ID:5242024
Related Subjects
20 FOSSIL-FUELED POWER PLANTS
01 COAL, LIGNITE, AND PEAT
COMBINED-CYCLE POWER PLANTS
FLUIDIZED-BED COMBUSTORS
PILOT PLANTS
CONSTRUCTION
DESIGN
COAL
FLUIDIZED-BED COMBUSTION
GAS TURBINES
MATERIALS HANDLING EQUIPMENT
STEAM TURBINES
CARBONACEOUS MATERIALS
CHEMICAL REACTIONS
COMBUSTION
COMBUSTORS
ENERGY SOURCES
EQUIPMENT
FOSSIL FUELS
FUELS
FUNCTIONAL MODELS
MACHINERY
MATERIALS
OXIDATION
POWER PLANTS
THERMAL POWER PLANTS
THERMOCHEMICAL PROCESSES
TURBINES
TURBOMACHINERY
200102* - Fossil-Fueled Power Plants- Power Cycles
014000 - Coal
Lignite
& Peat- Combustion
01 COAL, LIGNITE, AND PEAT
COMBINED-CYCLE POWER PLANTS
FLUIDIZED-BED COMBUSTORS
PILOT PLANTS
CONSTRUCTION
DESIGN
COAL
FLUIDIZED-BED COMBUSTION
GAS TURBINES
MATERIALS HANDLING EQUIPMENT
STEAM TURBINES
CARBONACEOUS MATERIALS
CHEMICAL REACTIONS
COMBUSTION
COMBUSTORS
ENERGY SOURCES
EQUIPMENT
FOSSIL FUELS
FUELS
FUNCTIONAL MODELS
MACHINERY
MATERIALS
OXIDATION
POWER PLANTS
THERMAL POWER PLANTS
THERMOCHEMICAL PROCESSES
TURBINES
TURBOMACHINERY
200102* - Fossil-Fueled Power Plants- Power Cycles
014000 - Coal
Lignite
& Peat- Combustion