Title: Engineer, design, construct, test and evaluate a pressurized fluidized bed pilot plant using high sulfur coal for production of electric power: Phase III. Pilot plant construction. Quarterly report, September 1-November 30, 1980

Technical Report ·
OSTI ID:5242024

Technical progress during the period September 1-November 30, 1980 on DOE Contract DE-AC21-76ET10417 is described. The design of the material handling equipment by the various vendors continues on schedule. Coal and dolomite feed system procurement was initiated. The SWEC Field Construction Office was established and site mobilization of the contractor for Bid Package No. 1 (Substructure) was initiated. Purchase orders were placed for the fabrication of all the PFB process recycle loop components. All preparatory work for placement of Bid Package No. 2, Structural Steel Erection, has been completed. Contract funding limitations have prevented placement of this purchase order.

Research Organization:
Curtiss-Wright Corp., Wood-Ridge, NJ (USA). Power Systems Div.
DOE Contract Number:
AC21-76ET10417
OSTI ID:
5242024
Report Number(s):
CW-WR-76-015.57A; FE-1726-57A; ON: DE82004269
Country of Publication:
United States
Language:
English