Salient electrical design features of the Magat Hydroelectric Project

Conference ·
OSTI ID:5117816

The Magat River Multipurpose project on the Luzon grid of the National Power Corporation of the Philippines consists of a four unit 450 MVA power-plant placed in service towards end of year 1983 and early 1984, providing an additional installed capacity of 360 MW to the existing generation peak capacity of 2478 MW of the Luzon grid, which is the country's Largest grid with an installed capacity of 3906 MW, the other two being those of Visayas and Mindanao with a total installed capacity of 1095 MW.

Research Organization:
Shawinigan Consultants Inc., Montreal, Que.
OSTI ID:
5117816
Report Number(s):
CONF-860705-
Country of Publication:
United States
Language:
English