Interim Reliability Evaluation Program: analysis of the Browns Ferry, Unit 1, nuclear plant. Main report
Technical Report
·
OSTI ID:5047497
A probabilistic risk assessment (PRA) was made of the Browns Ferry, Unit 1, nuclear plant as part of the Nuclear Regulatory Commission's Interim Reliability Evaluation Program (IREP). Specific goals of the study were to identify the dominant contributors to core melt, develop a foundation for more extensive use of PRA methods, expand the cadre of experienced PRA practitioners, and apply procedures for extension of IREP analyses to other domestic light water reactors. Event tree and fault tree analyses were used to estimate the frequency of accident sequences initiated by transients and loss of coolant accidents. External events such as floods, fires, earthquakes, and sabotage were beyond the scope of this study and were, therefore, excluded. From these sequences, the dominant contributors to probable core melt frequency were chosen. Uncertainty and sensitivity analyses were performed on these sequences to better understand the limitations associated with the estimated sequence frequencies. Dominant sequences were grouped according to common containment failure modes and corresponding release categories on the basis of comparison with analyses of similar designs rather than on the basis of detailed plant-specific calculations.
- Research Organization:
- EG and G Idaho, Inc., Idaho Falls (USA); Energy, Inc., Seattle, WA (USA)
- DOE Contract Number:
- AC07-76ID01570
- OSTI ID:
- 5047497
- Report Number(s):
- NUREG/CR-2802; EGG-2199; ON: DE82020539
- Country of Publication:
- United States
- Language:
- English
Similar Records
Interim reliability evaluation program, Browns Ferry 1
Interim reliability-evaluation program: analysis of the Millstone Point Unit 1 nuclear power plant. Volume I. Main report
RAMONA-3B application to Browns Ferry ATWS
Conference
·
Wed Dec 31 23:00:00 EST 1980
·
OSTI ID:5274879
Interim reliability-evaluation program: analysis of the Millstone Point Unit 1 nuclear power plant. Volume I. Main report
Technical Report
·
Fri Dec 31 23:00:00 EST 1982
·
OSTI ID:6345027
RAMONA-3B application to Browns Ferry ATWS
Conference
·
Mon Dec 31 23:00:00 EST 1984
·
OSTI ID:6476532
Related Subjects
21 SPECIFIC NUCLEAR REACTORS AND ASSOCIATED PLANTS
210100 -- Power Reactors
Nonbreeding
Light-Water Moderated
Boiling Water Cooled
22 GENERAL STUDIES OF NUCLEAR REACTORS
220900* -- Nuclear Reactor Technology-- Reactor Safety
ACCIDENTS
BROWNS FERRY-1 REACTOR
BWR TYPE REACTORS
ENRICHED URANIUM REACTORS
FAILURE MODE ANALYSIS
FAULT TREE ANALYSIS
MELTDOWN
MIXED SPECTRUM REACTORS
POWER REACTORS
REACTOR ACCIDENTS
REACTOR SAFETY
REACTORS
RELIABILITY
RISK ASSESSMENT
SAFETY
SYSTEM FAILURE ANALYSIS
SYSTEMS ANALYSIS
WATER COOLED REACTORS
WATER MODERATED REACTORS
210100 -- Power Reactors
Nonbreeding
Light-Water Moderated
Boiling Water Cooled
22 GENERAL STUDIES OF NUCLEAR REACTORS
220900* -- Nuclear Reactor Technology-- Reactor Safety
ACCIDENTS
BROWNS FERRY-1 REACTOR
BWR TYPE REACTORS
ENRICHED URANIUM REACTORS
FAILURE MODE ANALYSIS
FAULT TREE ANALYSIS
MELTDOWN
MIXED SPECTRUM REACTORS
POWER REACTORS
REACTOR ACCIDENTS
REACTOR SAFETY
REACTORS
RELIABILITY
RISK ASSESSMENT
SAFETY
SYSTEM FAILURE ANALYSIS
SYSTEMS ANALYSIS
WATER COOLED REACTORS
WATER MODERATED REACTORS