Skip to main content
U.S. Department of Energy
Office of Scientific and Technical Information

Thermal hydraulic evaluation of consolidating tank C-106 waste into tank AY-102

Technical Report ·
DOI:https://doi.org/10.2172/492107· OSTI ID:492107
This report describes the thermal hydraulic analysis performed to provide a technical basis in support of consolidation of tank C-106 waste into tank AY-102. Several parametric calculations were performed using the HUB and GOTH computer codes. First, the current heat load of tank AY-102 was determined. Potential quantities of waste transfer from tank C-106 were established to maintain the peak temperatures of consolidated sludge in tank AY-102 to remain within Operating Specification limits. For this purpose, it was shown that active cooling of the tank floor was essential and a secondary ventilation flow of 2,000 cfm should be maintained. Transient calculations were also conducted to evaluate the effects of ambient meteorological cyclic conditions on sludge peak temperature, and loss of ventilation systems. Detailed calculations were also performed to estimate the insulating concrete air channels cooling effectiveness and the resulting peak temperatures for the consolidated sludge in tank AY-102. Calculations are were also performed for a primary and secondary ventilation systems outage, both individually and combined to establish limits on outage duration. Because of its active cooling mode of operation, the secondary ventilation system limits the outage duration.
Research Organization:
Westinghouse Hanford Co., Richland, WA (United States)
Sponsoring Organization:
USDOE Office of Environmental Restoration and Waste Management, Washington, DC (United States)
DOE Contract Number:
AC06-96RL13200
OSTI ID:
492107
Report Number(s):
WHC-SD-WM-ER--534; ON: DE97052583
Country of Publication:
United States
Language:
English

Similar Records

W-320 Project thermal modeling
Technical Report · Mon Mar 17 23:00:00 EST 1997 · OSTI ID:326424

Review of Waste Retrieval Sluicing System Operations and Data for Tanks 241-C-106 and 241-AY-102
Technical Report · Tue Sep 26 00:00:00 EDT 2000 · OSTI ID:965194

Evaluation of waste temperatures in AWF tanks for bypass mode operation of the 702-AZ ventilation system, Project W-030
Technical Report · Wed Sep 10 00:00:00 EDT 1997 · OSTI ID:353235