SUMMARY OF HRT RUN 25

Technical Report ·
DOI:https://doi.org/10.2172/4823137· OSTI ID:4823137
Run 25 was the final period of power operational of the HRT. The reactor was operated for periods of 62, 8, 52, and 80 hours at 5 Mw with no outward indication of fuel and core and blanket average temperatures of 270 and 230 deg C, respectively. The uranium concentration in the was 1.7 to 2.0 g U/kg D/sub 2/O. Longer periods of operation were prevented by mechanical difficulties, notably with the fuel feed pump. While the reactor was subcritical after the last of the above runs, the upper patch in the core tank wall became dislodged, allowing greater core-to-blanket mixing. The resultant blanket uranium concentration was 2.9 g U/kg D/sub 2/O. The reactor was subsequently operated at April 28, 1961. The experiment was operated at high temperature for a total of 10,866 hours. The system was critical for a total of 8,841 hours and produced 16,295 Mwhours of power. The fuel, heavy water, and some corrosion specimens were recovered, and the reactor was stored in an assembled state. (auth)
Research Organization:
Oak Ridge National Lab., Tenn.
DOE Contract Number:
W-7405-ENG-26
NSA Number:
NSA-16-026618
OSTI ID:
4823137
Report Number(s):
ORNL-TM-173
Country of Publication:
United States
Language:
English

Similar Records

SUMMARY OF HRT RUNS 22, 23 AND 24
Technical Report · Wed Feb 28 23:00:00 EST 1962 · OSTI ID:4808872

HRT-CHEMICAL PLANT RUN-17 SUMMARY
Technical Report · Sat Feb 28 23:00:00 EST 1959 · OSTI ID:4275976

SUMMARY OF HRT RUN 14
Technical Report · Mon Jun 01 00:00:00 EDT 1959 · OSTI ID:4216106