skip to main content
OSTI.GOV title logo U.S. Department of Energy
Office of Scientific and Technical Information

Title: Filling temporary underground structures and workings at high-head hydro developments

Journal Article · · Hydrotechnical Construction
DOI:https://doi.org/10.1007/BF01545470· OSTI ID:457437

Examples of backfilling temporary underground structures and workings at hydroelectric stations in Russia are cited. Structures backfilled include temporary tunnels and auxiliary workings (shafts, chambers, etc.). Detail drawings illustrate many of the examples. Examples of backfilling at a number of hydropower plants are given; however, the main emphasis is on construction of Nurek Hydroelectric Station. 8 refs., 11 figs.

Sponsoring Organization:
USDOE
OSTI ID:
457437
Journal Information:
Hydrotechnical Construction, Vol. 28, Issue 6; Other Information: PBD: Dec 1994; TN: Translated from Gidrotekhnicheskoe Stroitel`stvo; No. 6, 31-38(Jun 1994)
Country of Publication:
United States
Language:
English