This standard provides requirements and guidelines for installation, inspection and testing activities that assure the quality of important mechanical parts of a nuclear power plant not covered by the ASME Boiler and Pressure Vessel Code, Section III, during construction. These parts include those mechanical systems and components whose satisfactory performance is required: for the plant to operate reliably; to prevent accidents that could cause undue risk to the health and safety of the public; or to mitigate the consequences of such accidents if they were to occur. The requirements of thts standard deal with the protection and control necessary to assure that the requisite quality of those important parts of the plant are prescrved from the time items are removed from storage or receiving ultil they are incorporated into the plant up to but not including fuel loading for PWR plants and the completion of cold functional testing for BWR and HTGR plants. (auth)
- Research Organization:
- Originating Research Org. not identified
- NSA Number:
- NSA-29-004668
- OSTI ID:
- 4392733
- Report Number(s):
- ANSI--N-45.2.8
- Country of Publication:
- Country unknown/Code not available
- Language:
- English
Similar Records
Supplementary quality assurance requirements for installation, inspection and testing of mechanical equipment and systems for the construction phase of nuclear power plants - reaffirmed 1980
Requirements for the calibration and control of measuring and test equipment used in the construction and maintenance of nuclear power generating stations
Supplementary quality assurance requirements for installation, inspection, and testing of structural concrete and structural steel during the construction phase of nuclear power plants. Draft 3, Rev. 0
Book
·
Wed Dec 31 23:00:00 EST 1980
·
OSTI ID:6865737
Requirements for the calibration and control of measuring and test equipment used in the construction and maintenance of nuclear power generating stations
Book
·
Wed Dec 31 23:00:00 EST 1980
·
OSTI ID:6946989
Supplementary quality assurance requirements for installation, inspection, and testing of structural concrete and structural steel during the construction phase of nuclear power plants. Draft 3, Rev. 0
Book
·
Sun Dec 31 23:00:00 EST 1972
·
OSTI ID:4410900