ARMY GAS-COOLED REACTOR SYSTEMS PROGRAM. Monthly Progress Report for July 1960
Technical Report
·
OSTI ID:4122662
Power ascension in the Gas-cooled Reactor Experiment was successfully completed to a limited power of 1.85 Mw. In development studies on the Army Reactor (ML-1), problems were encountered with perosity in the lead castings for the shield. The increase in pressure drop across the recuperator, due to the finning operation, was reduced slightly by modifying the fabrication process. The functions of the gas make-up skid and the gas storage skid are to be consolidated. All three blowers on the BMI-16 test loop, operating with a test element foilowing removal of the I-3P, became inoperable in less than 200 hr. A peak surface temperature of 1570 deg F was measured for the IB-2T-1 element. Corrosion tests were performed on Hastelloy X, Inconel, and Inconel 702 at 68 deg F in the ML-1 reference coolant gas. The specimens were also subjected to the reference gas for 5000 hr at 1750DEF. (For preceding period see IDO-28558.) (C.J.G.)
- Research Organization:
- Aerojet-General Nucleonics, San Ramon, Calif.
- NSA Number:
- NSA-15-001054
- OSTI ID:
- 4122662
- Report Number(s):
- IDO-28559
- Country of Publication:
- United States
- Language:
- English
Similar Records
ARMY GAS-COOLED REACTOR SYSTEMS PROGRAM. EVALUATION OF LONG TERM GAS CORROSION OF HEAT RESISTANT ALLOYS FOR USE AS GAS-COOLED REACTOR FUEL CLADDING
ARMY GAS-COOLED REACTOR SYSTEMS PROGRAM SEMIANNUAL PROGRESS REPORT FOR JANUARY 1-JUNE 30, 1960
ARMY GAS-COOLED REACTOR SYSTEMS PROGRAM. Monthly Progress Report for September 1960
Technical Report
·
Sun Mar 31 23:00:00 EST 1963
·
OSTI ID:4695564
ARMY GAS-COOLED REACTOR SYSTEMS PROGRAM SEMIANNUAL PROGRESS REPORT FOR JANUARY 1-JUNE 30, 1960
Technical Report
·
Sun Jul 31 00:00:00 EDT 1960
·
OSTI ID:4135055
ARMY GAS-COOLED REACTOR SYSTEMS PROGRAM. Monthly Progress Report for September 1960
Technical Report
·
Thu Sep 01 00:00:00 EDT 1960
·
OSTI ID:4094869