HEAVY MODERATED POWER REACTORS. Progress Report for September 1960
Technical Report
·
OSTI ID:4111705
At the end of Sept. l960, construction of the Heavy Water Components Test Reactor (HWCTR) was 41% complete. Hydraulic tests of one of the two main D/ sub 2/O pumps for the facility were concluded satisfactorily. Extrusion billet designs that appear to afford satisfactory control of cladding thickness have been devised at Nuclear Metals, Inc., for both sizes of uranium metal tube desired for HWCTR irradiation tests. The first 10-ft-long fuel tube of compacted uranium oxide in Zircaloy was fabricated at the Savannah River Laboratory by a combination of vibratory compaction and swaging. The average oxide density in this tube was 91.8% of theoretical. (For preceding period see DP-535.) (auth)
- Research Organization:
- Du Pont de Nemours (E.I.) & Co. Atomic Energy Div., Wilmington, Del.
- NSA Number:
- NSA-15-005813
- OSTI ID:
- 4111705
- Report Number(s):
- DP-545
- Country of Publication:
- United States
- Language:
- English
Similar Records
HEAVY WATER MODERATED POWER REACTORS PROGRESS REPORT, DECEMBER 1960
HEAVY WATER MODERATED POWER REACTORS PROGRESS REPORT AUGUST 1960
HEAVY WATER MODERATED POWER REACTORS. Progress Report for June 1960
Technical Report
·
Tue Feb 28 23:00:00 EST 1961
·
OSTI ID:4065011
HEAVY WATER MODERATED POWER REACTORS PROGRESS REPORT AUGUST 1960
Technical Report
·
Mon Oct 31 23:00:00 EST 1960
·
OSTI ID:4094913
HEAVY WATER MODERATED POWER REACTORS. Progress Report for June 1960
Technical Report
·
Sat Oct 01 00:00:00 EDT 1960
·
OSTI ID:4124001