PERIODIC PRIMARY PLANT LEAK RATE TEST. CORE 1, SEED 1. Test Results T- 641102

Technical Report ·
OSTI ID:4055863

Tests were carried out to determine the magnitude and location of primary system leakage. The system leak rates were 4.1 and 14.1 gallons per hour for two tests. A relief valve leak rate of 20.6 gallons per hour of primary system fluid existed for the 6 relief valves tested during the first test. All valves appeared to be contributing to the leakage. Similar data obtained during the second test indicated a relief valve leak rate of 0.4 gallons per hour for 7 valves tested, and only one appeared to be leaking. (M.C.G.)

Research Organization:
Duquesne Light Co., Shippingport, Penna.
NSA Number:
NSA-15-020444
OSTI ID:
4055863
Report Number(s):
TID-12826; DLCS-2110130; DLCS-
Country of Publication:
Country unknown/Code not available
Language:
English

Similar Records

PERIODIC PRIMARY PLANT LEAK RATE TEST. CORE I, SEED 2. Test Results T- 641102
Technical Report · Sun Jan 29 23:00:00 EST 1961 · OSTI ID:4021891

PERIODIC REACTOR PLANT LEAK RATE TEST. CORE I, SEED 2. Test Results T- 641102
Technical Report · Thu Jan 19 23:00:00 EST 1961 · OSTI ID:4027734

PERIODIC REACTOR PLANT LEAK RATE TEST. CORE I, SEED 2. TEST RESULTS T- 641102
Technical Report · Thu Jan 19 23:00:00 EST 1961 · OSTI ID:4073757