PERIODIC PRIMARY PLANT LEAK RATE TEST. CORE 1, SEED 1. Test Results T- 641102
Technical Report
·
OSTI ID:4055863
Tests were carried out to determine the magnitude and location of primary system leakage. The system leak rates were 4.1 and 14.1 gallons per hour for two tests. A relief valve leak rate of 20.6 gallons per hour of primary system fluid existed for the 6 relief valves tested during the first test. All valves appeared to be contributing to the leakage. Similar data obtained during the second test indicated a relief valve leak rate of 0.4 gallons per hour for 7 valves tested, and only one appeared to be leaking. (M.C.G.)
- Research Organization:
- Duquesne Light Co., Shippingport, Penna.
- NSA Number:
- NSA-15-020444
- OSTI ID:
- 4055863
- Report Number(s):
- TID-12826; DLCS-2110130; DLCS-
- Country of Publication:
- Country unknown/Code not available
- Language:
- English
Similar Records
PERIODIC PRIMARY PLANT LEAK RATE TEST. CORE I, SEED 2. Test Results T- 641102
PERIODIC REACTOR PLANT LEAK RATE TEST. CORE I, SEED 2. Test Results T- 641102
PERIODIC REACTOR PLANT LEAK RATE TEST. CORE I, SEED 2. TEST RESULTS T- 641102
Technical Report
·
Sun Jan 29 23:00:00 EST 1961
·
OSTI ID:4021891
PERIODIC REACTOR PLANT LEAK RATE TEST. CORE I, SEED 2. Test Results T- 641102
Technical Report
·
Thu Jan 19 23:00:00 EST 1961
·
OSTI ID:4027734
PERIODIC REACTOR PLANT LEAK RATE TEST. CORE I, SEED 2. TEST RESULTS T- 641102
Technical Report
·
Thu Jan 19 23:00:00 EST 1961
·
OSTI ID:4073757