Wabash River coal gasification repowering project: Public design report

Technical Report ·
DOI:https://doi.org/10.2172/383625· OSTI ID:383625

The Wabash River Coal Gasification Repowering Project (the Project), conceived in October of 1990 and selected by the US Department of Energy as a Clean Coal IV demonstration project in September 1991, is expected to begin commercial operations in August of 1995. The Participants, Destec Energy, Inc., (Destec) of Houston, Texas and PSI Energy, Inc., (PSI) of Plainfield, Indiana, formed the Wabash River Coal Gasification Repowering Project Joint Venture (the JV) to participate in the DOE`s Clean Coal Technology (CCT) program by demonstrating the coal gasification repowering of an existing 1950`s vintage generating unit affected by the Clean Air Act Amendments (CAAA). The Participants, acting through the JV, signed the Cooperative Agreement with the DOE in July 1992. The Participants jointly developed, and separately designed, constructed, own, and will operate an integrated coal gasification combined cycle (CGCC) power plant using Destec`s coal gasification technology to repower Unit {number_sign}1 at PSI`s Wabash River Generating Station located in Terre Haute, Indiana. PSI is responsible for the new power generation facilities and modification of the existing unit, while Destec is responsible for the coal gasification plant. The Project demonstrates integration of the pre-existing steam turbine generator, auxiliaries, and coal handling facilities with a new combustion turbine generator/heat recovery steam generator tandem and the coal gasification facilities.

Research Organization:
Wabash Coal Gasification Repowering Project Joint Venture, Houston, TX (United States)
Sponsoring Organization:
USDOE, Washington, DC (United States)
DOE Contract Number:
FC21-92MC29310
OSTI ID:
383625
Report Number(s):
DOE/MC/29310--5260; ON: DE96011350
Country of Publication:
United States
Language:
English

Similar Records

Wabash River Coal Gasification Repowering Project. Topical report, July 1992--December 1993
Technical Report · Fri Dec 31 23:00:00 EST 1993 · OSTI ID:10178075

The Wabash River Coal Gasification Repowering Project: An investment in the future
Conference · Fri Dec 30 23:00:00 EST 1994 · OSTI ID:75434

CGCC repowering nears commercial startup
Journal Article · Thu Jun 01 00:00:00 EDT 1995 · Power Engineering (Barrington) · OSTI ID:72457