Fast Flux Test Facility (FFTF) standby plan

Technical Report ·
DOI:https://doi.org/10.2172/289371· OSTI ID:289371

The FFTF Standby Plan, Revision 0, provides changes to the major elements and project baselines to maintain the FFTF plant in a standby condition and to continue washing sodium from irradiated reactor fuel. The Plan is consistent with the Memorandum of Decision approved by the Secretary of Energy on January 17, 1997, which directed that FFTF be maintained in a standby condition to permit the Department to make a decision on whether the facility should play a future role in the Department of Energy`s dual track tritium production strategy. This decision would be made in parallel with the intended December 1998 decision on the selection of the primary, long- term source of tritium. This also allows the Department to review the economic and technical feasibility of using the FFTF to produce isotopes for the medical community. Formal direction has been received from DOE-RL and Fluor 2020 Daniel Hanford to implement the FFTF standby decision. The objective of the Plan is maintain the condition of the FFTF systems, equipment and personnel to preserve the option for plant restart within three and one-half years of a decision to restart, while continuing deactivation work which is consistent with the standby mode.

Research Organization:
Fluor Daniel Hanford, Inc., Richland, WA (United States)
Sponsoring Organization:
USDOE Office of Environmental Restoration and Waste Management, Washington, DC (United States)
DOE Contract Number:
AC06-96RL13200
OSTI ID:
289371
Report Number(s):
HNF-SD-FF-SSP--056; ON: DE98059652; BR: EX7005000; CNN: DE-AC06-96RL13200
Country of Publication:
United States
Language:
English

Similar Records

FFTF and Advanced Reactors Transition Program Resource Loaded Schedule
Technical Report · Mon Oct 30 23:00:00 EST 2000 · OSTI ID:805395

Advanced Reactors Transition program fiscal year 1998 multi-year work plan
Technical Report · Thu Sep 25 00:00:00 EDT 1997 · OSTI ID:344980

Operational readiness review implementation plan for K Basin sludge water system