High SO{sub 2} removal efficiency testing. Technical progress report, January--March 1996
This project involves testing at six full-scale utility flue gas desulfurization (FGD) systems, to evaluate low capital cost upgrades that may allow these systems to achieve up to 98% SO{sub 2} removal efficiency. The upgrades being evaluated primarily involve using performance additives in the FGD systems. The base project involved testing at the Tampa Electric Company Big Bend station. All five potential options to the base program have been exercised by DOE, involving testing at Hooiser Energy`s Merom Station (Option I), Southwestern Electric Power Company`s Pirkey Station (Option II), PSI Energy`s Gibson Station (Option III), Duquesne Light`s Elrama Station (Option IV), and New York State Electric and Gas Corporation`s Kintigh Station (Option V). The originally planned testing has been completed for all six sites.
- Research Organization:
- Radian Corp., Austin, TX (United States)
- Sponsoring Organization:
- USDOE, Washington, DC (United States)
- DOE Contract Number:
- AC22-92PC91338
- OSTI ID:
- 288845
- Report Number(s):
- DOE/PC/91338--T16; ON: DE96050057
- Country of Publication:
- United States
- Language:
- English
Similar Records
High SO{sub 2} removal efficiency testing. Quarterly report, July - September 1996
High SO(2) removal efficiency testing. Technical progress report, March - May 1996
High SO{sub 2} removal efficiency testing. Quarterly status report, April-June 1995
Technical Report
·
Mon Jul 01 00:00:00 EDT 1996
·
OSTI ID:353750
High SO(2) removal efficiency testing. Technical progress report, March - May 1996
Technical Report
·
Mon Dec 30 23:00:00 EST 1996
·
OSTI ID:468454
High SO{sub 2} removal efficiency testing. Quarterly status report, April-June 1995
Technical Report
·
Fri Jul 14 00:00:00 EDT 1995
·
OSTI ID:155340