skip to main content
OSTI.GOV title logo U.S. Department of Energy
Office of Scientific and Technical Information

Title: Remote Technology to Retrieve Waste Below the 324 Building at the Hanford Site - 19622

Conference ·
OSTI ID:23005462
; ;  [1];  [2]
  1. CH2M HILL Plateau Remediation Company - CHPRC, Richland, WA 99352 (United States)
  2. US DOE (United States)

The Waste Technology Engineering Laboratory (324 Building) is a Category 2 Nuclear Facility at Hanford. The 324 Building Disposition Project is responsible for the removal and remedial actions under CERCLA. Additionally, there are RCRA Dangerous Waste Management Units which the CERCLA actions are presumed to satisfy. The Radiochemical Engineering Complex (REC) is a group of four hot cells (A, B, C and D Cells) with an interconnecting airlock inside of the 324 Building. Underneath the REC B-Cell are contaminated soils that have an estimated 12,793 R/Hr dose rate and remediation is under CERCLA 300-FF-2 Operable Unit. The current action consists of debris removal from the floor of B-Cell, B-Cell floor removal, and excavation of the soils beneath the floor to a depth of up to twelve feet with four Remote Excavator Arms (REA). This paper provides insight into the preparation and performance of high tolerance core drilling into a hot cell complex. Installation of the REA Through Support (REA TS) mechanism through the 4'-6' concrete shield walls is a complex series of tasks with demanding tolerances at each of four locations around the perimeter of B-Cell. The use of training mock ups was included in the completion of this work. The REA TS is two 11 inch diameter high strength steel sleeves that have expandable collars at each end allowing the interstitial space between the outside of the sleeve and inside of the core drill to be grouted to form a substantial structural connection, and a 10 inch pipe with hydraulic hoses to power the REA. There are three cores required for each REA location. The REAs themselves are customized excavator arms, mounted on support columns to be used in the excavation and transfer of the contaminated soil into storage facilities. The tasks for the installation of the REA TSs are: 1) Characterization of B-Cell Cubicles. 2) Embedded Pipe Fill. 3) Interference Removal. a. Internal Walls, b. External Walls. 4) Core Drilling. 5) Go/No-Go gauge, and video inspection. 6) Installation of REA Through Support Assembly. The 324 Building REC Hot Cells have internal, external, and embedded utilities throughout the shield walls in conflict with the REA TS locations. Some of the embedded utilities have connection points inside of the B-Cell Cubicles. There were two separate issues at the conflicted locations. The first issue was the core drill cooling water would flow along the embedded utility potentially spreading legacy chemical and radiological contamination to areas of the facility that was unwanted. The second issue was that the REA TS required a substantial structural connection to the B-Cell wall, the cored diameter is larger than the REA TS and these interstitial areas required a full grouted connection. The embedded utilities posed a hazard that if unfilled, the interstitial grout would flow into the embedded utility and destabilize the required grouted structural connection. The B-Cell Cubicles had not been opened in over 10 years. A mockup was completed to install a glovebag over the cubicle opening and then to verify functionality and port requirements. The embedded utility pipe connections in the cubicles were then opened inside a glovebag to verify the correct connection points, connection method for future embedded pipe fill material delivery system, radiological characterization, and air flow to show that the embedded utility pipes were not blocked and would not pressurize. The embedded pipe fill material and grout system was mocked up and run several times to verify methodology and functionality. The B-Cell Cubicles were then reentered and the embedded utility pipe fill was completed using a hand pump. External interferences at the core drill locations were removed using standard interference removal techniques. Internal interferences at the core drill locations were removed using a remote cutting tool that was controlled through the use of the B-Cell crane, remote cameras and remote lighting. The core drilling was mocked up two separate times, the project's purpose built 'Mock Up Facility' was core drilled to verify tolerances and methodology prior to subcontract award, the core drill subcontractor built a 'dummy wall' to train and practice on achieving the demanding tolerances, coordinated alignments between the cores, short term and long term dose shielding techniques, and contamination control techniques. A core drill template, and additional anchoring techniques were used to maximize accuracy and precision of the REA TS core drills. A 'Go/No-Go' gauge was built and installed at each of the four REA TS locations to verify that the core drill met tolerances. The core drill locations were visually inspected using a boroscope. The REA TS installation was mocked up at the projects 'Mock Up Facility' beginning with basic hazard controls, then with intermediate hazard controls, and finally with full occupational safety, industrial hygiene, and radiological controls. The REA TSs were installed and grouted into place. (authors)

Research Organization:
WM Symposia, Inc., PO Box 27646, 85285-7646 Tempe, AZ (United States)
OSTI ID:
23005462
Report Number(s):
INIS-US-21-WM-19622; TRN: US21V1389045796
Resource Relation:
Conference: WM2019: 45. Annual Waste Management Conference, Phoenix, AZ (United States), 3-7 Mar 2019; Other Information: Country of input: France; available online at: https://www.xcdsystem.com/wmsym/2019/index.html
Country of Publication:
United States
Language:
English