Title: Environmental Cleanup of the East Tennessee Technology Park Year One - Execution with Certainty SM - 13120

Conference ·
OSTI ID:22224904
 [1]
  1. URS - CH2M Oak Ridge LLC, P.O. Box 4699, Oak Ridge, TN 37831-7294 (United States)

On August 1, 2011, URS - CH2M Oak Ridge LLC (UCOR) began its five-year, $1.4 billion cleanup of the East Tennessee Technology Park (ETTP), located on the U.S. Department of Energy's (DOE) Oak Ridge Reservation in Tennessee. UCOR will close out cleanup operations that began in 1998 under a previous contract. When the Contract Base scope of work [1] is completed in 2016, the K-25 gaseous diffusion building will have been demolished and all waste dispositioned, demolition will have started on the K-27 gaseous diffusion building, all contact-handled and remote-handled transuranic waste in inventory (approximately 500 cubic meters) will have been transferred to the Transuranic Waste Processing Center, previously designated 'No-Path-To-Disposition Waste' will have been dispositioned to the extent possible, and UCOR will have managed DOE Office of Environmental Management (EM)- owned facilities at ETTP, Oak Ridge National Laboratory (ORNL), and the Y-12 National Security Complex in a safe and cost-effective manner. Since assuming its responsibilities as the ETTP cleanup contractor, UCOR has completed its life-cycle Performance Measurement Baseline; received its Earned Value Management System (EVMS) certification; advanced the deactivation and demolition (D and D) of the K-25 gaseous diffusion building; recovered and completed the Tank W-1A and K-1070-B Burial Ground remediation projects; characterized, packaged, and shipped contact-handled transuranic waste to the Transuranic Waste Processing Center; disposed of more than 90,000 cubic yards of cleanup waste while managing the Environmental Management Waste Management Facility (EMWMF); and provided operations, surveillance, and maintenance activities at DOE EM facilities at ETTP, ORNL, and the Y-12 National Security Complex. Project performance as of December 31, 2012 has been excellent: - Cost Performance Index - 1.06; - Schedule Performance Index - 1.02. At the same time, since safety is the foundation of all cleanup work, UCOR's safety record goes hand in hand with its excellent project performance. Through calendar year 2012, UCOR's recordable injury rate was 0.33, and the company has worked close to 4 million hours without a lost work day injury. UCOR's safety record is one of the best in the DOE EM Complex. This performance was due, in large part, to the people and processes URS and CH2M HILL, the parent companies of UCOR, brought to the project. Key approaches included: - Selected and deployed experienced staff in key leadership positions throughout the organization; - Approached 'Transition' as the 'true' beginning of the cleanup project - kicking off a number of project initiatives such as Partnering, PMB development, D and D Plan execution, etc. - Established a project baseline for performance measurement and obtained EVMS certification in record time; - Determined material differences and changed conditions that warranted contract change - then quickly addressed these changes with the DOE client; - Aligned the project and the contract within one year - also done in record time; - Implemented Safety Trained Supervisor and Safety Conscious Work Environment Programs, and kicked off the pursuit of certification under DOE's Voluntary Protection Program. (authors)

Research Organization:
WM Symposia, 1628 E. Southern Avenue, Suite 9-332, Tempe, AZ 85282 (United States)
OSTI ID:
22224904
Report Number(s):
INIS-US-13-WM-13120; TRN: US14V0342045859
Resource Relation:
Conference: WM2013: Waste Management Conference: International collaboration and continuous improvement, Phoenix, AZ (United States), 24-28 Feb 2013; Other Information: Country of input: France; 5 refs.
Country of Publication:
United States
Language:
English