Title: Experience of the nuclear reactors (environmental impact assessment for decommissioning) regulations 1999, as amended, in Great Britain

Conference ·
OSTI ID:21156520
; ;  [1]
  1. Nuclear Directorate, Health and Safety Executive (United Kingdom)

Available in abstract form only. Full text of publication follows: In Great Britain, the Nuclear Reactors (Environmental Impact Assessment for Decommissioning) Regulations 1999 as amended 2006 (EIADR) requires assessment of the potential environmental impacts of projects to decommission nuclear power stations and reactors. The Health and Safety Executive (HSE) is the competent authority for EIADR. The EIADR implement European Council Directive 85/337/EEC (the EIA Directive) as amended by Council Directive 97/11/EC and Council Directive 2003/35/EC the (Public Participation Directive). The purpose of the EIADR is to assess environmental effects of nuclear reactor decommissioning projects, involve the public through consultation, and make the decision-making process open and transparent. Under the regulations, any licensee wishing to begin to decommission or dismantle a nuclear power station, or other civil nuclear reactor, must apply to HSE for consent to carry out the decommissioning project, undertake an environmental impact assessment and prepare an environmental statement that summarises the environmental effects of the project. HSE will consult on the environmental statement. So far under the EIADR there have been six consents granted for decommissioning projects for Magnox Power Stations. These stations have been required as a condition of consent to submit an Environmental Management Plan on an annual basis. This allows the project to be continually reviewed and assessed to ensure that the licensee can provide detail as agreed during the review of the environmental statement and that any changes to mitigation measures are detailed. This paper summarises the EIADR process, giving particular emphasis to public participation and the decision making process, and discusses HSE's experience of EIADR with reference to specific environmental issues raised by stakeholders and current developments. (authors)

Research Organization:
American Society of Mechanical Engineers (ASME), Three Park Avenue, New York, NY 10016-5990 (United States); Technological Institute of the Royal Flemish Society of Engineers (TI-K VIV), Het Ingenieurshuis, Desguinlei 214, 2018 Antwerp (Belgium); Belgian Nuclear Society (BNS) - ASBL-VZW, c/o SCK-CEN, Avenue Hermann Debrouxlaan, 40 - B-1160 Brussels (Belgium)
OSTI ID:
21156520
Resource Relation:
Conference: ICEM'07: 11. International Conference on Environmental Remediation and Radioactive Waste Management, Bruges (Belgium), 2-6 Sep 2007; Other Information: Country of input: France; Proceedings may be ordered from ASME Order Department, 22 Law Drive, P.O. Box 2300, Fairfield, NJ 07007-2300 (United States)
Country of Publication:
United States
Language:
English