Startup and initial operation of a DFGD and pulse jet fabric filter system on Cokenergy's Indiana Harbor coke oven off gas system

Conference ·
OSTI ID:20013465

This paper describes the design, initial operation and performance testing of a Dry Flue Gas Desulfurization (DFGD) and Modular Pulse Jet Fabric Filter (MPJFF) system installed at Cokenergy's site in East Chicago, Indiana. The combined flue gas from the sixteen (16) waste heat recovery boilers is processed by the system to control emissions of sulfur dioxide and particulates. These boilers recover energy from coke oven off gas from Indiana Harbor Coke Company's coke batteries. The DFGD system consists of two 100% capacity absorbers. Each absorber vessel uses a single direct drive rotary atomizer to disperse the lime slurry for SO{sub 2} control. The MPJFF consists of thirty two (32) modules arranged in twin sixteen-compartment (16) units. The initial start up of the DFGD/MPJFF posed special operational issues due to the low initial gas flows through the system as the four coke oven batteries were cured and put in service for the first time. This occurred at approximately monthly intervals beginning in March 1998. A plan was implemented to perform a staged startup of the DFGD and MPJFF to coincide with the staged start up of the coke batteries and waste heat boilers. Operational issues that are currently being addressed include reliability of byproduct removal. Performance testing was conducted in August and September 1998 at the inlet of the system and the outlet stack. During these tests, particulate, SO{sub 2}, SO{sub 3}, and HCI emissions were measured simultaneously at the common DFGD inlet duct and the outlet stack. Measurements were also taken for average lime, water, and power consumption during the tests as well as system pressure losses. These results showed that all guarantee parameters were achieved during the test periods. The initial operation and performance testing are described in this paper.

Research Organization:
Marsulex Environmental Technologies (US)
OSTI ID:
20013465
Country of Publication:
United States
Language:
English

Similar Records

Nonrecovery cokemaking/cogeneration complex at Inland Steel scheduled to start up in mid-1998
Journal Article · Sun Nov 30 23:00:00 EST 1997 · Iron and Steel Engineer · OSTI ID:603816

Method of operating horizontal coke oven batteries
Patent · Tue Sep 22 00:00:00 EDT 1981 · OSTI ID:5867397

High-speed smokeless coke oven battery
Patent · Tue Sep 01 00:00:00 EDT 1981 · OSTI ID:5788319