skip to main content
OSTI.GOV title logo U.S. Department of Energy
Office of Scientific and Technical Information

Title: Liquid Salt Combined-Cycle Pilot Plant Design

Technical Report ·
DOI:https://doi.org/10.2172/1854364· OSTI ID:1854364

The work described in this report is responsive to the Office of Fossil Energy program ‘Energy Storage for Fossil Power Generation.’ This Phase I report has been prepared by Pintail Power LLC, with support from Nexant ECA, Electric Power Research Institute (EPRI) and Southern Company Services as a deliverable for the U.S. Department of Energy for NETL Award DE-FE-00320016. The Liquid Salt Combined Cycle™ (LSCC™) technology provides large-scale energy storage integrated with Fossil Electric Generating Units (FEGUs) to meet critical needs in the energy transition by providing: • the lowest cost large-scale storage for time-shifting of renewable energy, • superior fuel efficiency to reduce GHGs from dispatchable resources, • flexible capacity and ramping to balance variability of wind and solar resources, • essential grid stability services to assure reliability of a low-carbon grid. The LSCC approach: • employs equipment that has already been proven in utility service, • uses safe, non-toxic, non-degrading, perpetual-life storage medium, • leverages and repurposes existing FEGU assets, • expands the value stack of energy storage to reduce market, financing, and commodity risks. Pintail Power has developed the LSCC technology to meet the need for reliable, efficient, and cost-effective integration of Variable Renewable Energy (VRE) into a low-carbon electric grid by coupling proven thermal energy storage with proven gas turbines, steam turbines, and heat transfer equipment. This novel approach is intended to address the key issues facing the grid and operators of renewable and fossil generating units including: • Overgeneration and curtailment of renewables, • Need for fast ramping dispatchable resources, • Improved efficiency and flexibility of fossil units, • Additional peaking capacity to support electrification of transportation and heating, • Provision of reliability services to support high penetration of VRE, especially synchronous inertia and fast frequency response. A Technology Readiness assessment by EPRI confirmed that LSCC technology consists of commercially proven hardware used in industrial and utility applications. Although the novel LSCC approach has not yet been demonstrated as a complete system, interfaces between major components have been conservatively specified. A Phase III pilot is planned to demonstrate equipment integration and operation. The patented innovation is removal of the evaporator section from the exhaust heat recovery system, with the evaporation performed by stored energy in a separate steam generator. This arrangement couples renewable and fossil power generation via long-duration energy storage to deliver cost, performance, and operational synergies, including superior charging and discharging flexibility, reduced fuel consumption and lower CO2 emissions compared to conventional Combined Cycle Power Plants, and low-cost, large-scale energy storage. The LSCC technology is composed of proven equipment integrated with gas turbine exhaust heat in a novel system. During charging, electric heaters raise the salt temperature as it flows from the Cold Salt Tank to the Hot Salt Tank. During discharging, hot salt produces steam from feedwater that is heated with gas turbine exhaust, which also superheats steam to drive a steam turbine. LSCC technology can be added to any combustion-turbine to integrate renewable energy, provide needed grid services, and increase the value of fossil electric generating units based on the technology’s following attributes: • Long-duration storage enables time-shifting of VRE to avoid curtailment and impairment of renewable assets. • Long storage duration combined with fast-charging capability increases arbitrage opportunities by storing more energy when the price is low and discharging more hours when the price is high. • Long storage duration allows resource adequacy to be supplied across multiple days to increase reliability and reduce risk. • The stored energy reduces fuel heat rate and GHG emissions, and increases merit, so the LSCC dispatches earlier and longer to increase the plant’s capacity factor and asset value. • The stored energy enables pre-heating and startup of the steam cycle, without operating the gas turbine, to enable fast startup and ramping when dispatched for discharge. • The steam turbine can operate without the gas turbine so it can provide valuable synchronous inertia during charging without consuming fuel. • Fast frequency response and regulation services can be provided during charging using solid-state heater and pump controls to vary the charge power input in response to grid signals. • The LSCC system can be configured for resilience including black start, islanded/micro-grid operation, and even self-recharging of storage using either gas turbine power or gas turbine exhaust heat. The commercialization plan is to add LSCC technology to existing simple cycle gas turbine power plants with the 50MW GE LM6000 aero-derivative gas turbine as the reference design basis. A Techno-economic assessment of the reference design evaluated the benefits (Levelized Avoided Cost of Energy) and costs (Levelized Cost of Energy). The plant definition included all major systems and budgetary vendor quotes. Pintail Power and NexantECA developed the overall cost estimate for the LSCC plant up to the total plant cost level, following the DOE-NETL cost estimate guidelines at AACE Class 3 (-20%/+30%). This includes the equipment cost, bulk material, direct and indirect labor costs to arrive at the bare erected cost. Engineering costs are factored from the BEC and added to it to arrive at the EPC cost. Process and project contingencies were then factored from the EPC cost and rolled-up to yield the total plant cost of $$\$$$$184 million for 1746 MWh of discharge electricity. • At $$\$$$$105/kWh, the reference plant costs less than any of the Energy Storage Systems evaluated by PNNL in 2020 for the Energy Storage Grand Challenge. Operations and Maintenance cost estimates were scaled from combined cycle practice, assuming that the LSCC unit was co-located with and sharing some labor expense with other units, to arrive at $$\$$$$2.2 million per year. Plant economics were evaluated using prices from the ERCOT Day-Ahead Market for calendar year 2019 (excluding the market disruptions from the COVID pandemic and the February 2020 deep freeze event). Assuming economic dispatch in the ERCOT Day-Ahead market, the reference plant capacity factor would have discharged for 2777 hours at 91.9 MW, a 31.66% capacity factor, with a marginal cost of $$\$$$$25.59/MWh, and a LACE of $$\$$$$82.41/MWh. Fixed charges were calculated according to EIA guidelines to arrive at an LCOE of $$\$$$$83.48. The benefit-to-cost ratio of 0.99 suggests that the reference plant would have been cost-effective and competitive in the market. EPRI interviewed selected utilities to gauge the need for, applicability of and interest in the LSCC system. Several utilities are currently managing increased load growth along with the inclusion of increasing levels of renewable generation, putting pressure on conventional generation by requiring increased turndown requirements and ultimately lower capacity factors. All of the utilities interviewed have CO2 reduction targets in the 2030-2050 timeframe that will severely limit the participation of fossil generation and require better utilization of carbon free generation. While there is limited opportunity for storage in the current markets, the utilities interviewed stated that there will be a substantial need for long duration energy storage in the future given the expected trends. Utilizing an energy storage system will generally be preferred over new gas capacity in some cases, with the capabilities of the LSCC system being a potential option for retrofit to existing simple cycle gas turbine units, allowing them to deliver greater participation in the market with lower carbon intensity. A technology gap assessment and technology maturation plan identified a pilot-scale demonstration as the final step before commercialization. Key gaps to be addressed during the Phase II FEED (Front-End Engineering Design) are component selection and design, commissioning procedures, and operational procedures and the control system for LSCC charging and discharging. The project team has been expanded to include Wood Group PLC as EPC. The proposed Phase II work leads to a pilot-scale engineering demonstration (TRL 6) to be conducted at Southern Company’s Plant Rowan, where the prototype system will perform “all the functions that will be required of the operational system.” The proposed pilot will facilitate commercialization (TRL-9) by scale-up to utility-scale systems integrated with peaking GTs or directly to facility scale systems using industrial GTs. The conceptual design for the pilot plant focuses on the novel integration aspects of LSCC technology. A slipstream of gas turbine exhaust will feed a waste heat recovery unit coupled to a molten salt steam generator heated by stored energy. The pilot is intended to demonstrate all key operating modes of the LSCC technology during charging, discharging and standby. The pilot equipment will be approximately one-seventh scale of the LM6000 commercial target and is expected to have commercial off-ramp potential for facility-scale applications.

Research Organization:
Electric Power Research Inst. (EPRI), Palo Alto, CA (United States)
Sponsoring Organization:
USDOE Office of Fossil Energy (FE)
Contributing Organization:
Pintail Power, LLC; Southern Company; NexantECA
DOE Contract Number:
FE0032016
OSTI ID:
1854364
Report Number(s):
DOE-EPRI-32016-1
Country of Publication:
United States
Language:
English