Nuclear fuel reprocessing deactivation plan for the Idaho Chemical Processing Plant, Revision 1

Technical Report ·
DOI:https://doi.org/10.2172/137287· OSTI ID:137287
The decision was announced on April 28, 1992 to cease all United States Department of Energy (DOE) reprocessing of nuclear fuels. This decision leads to the deactivation of all fuels dissolution, solvent extraction, krypton gas recovery operations, and product denitration at the Idaho Chemical Processing Plant (ICPP). The reprocessing facilities will be converted to a safe and stable shutdown condition awaiting future alternate uses or decontamination and decommissioning (D&D). This ICPP Deactivation Plan includes the scope of work, schedule, costs, and associated staffing levels necessary to achieve a safe and orderly deactivation of reprocessing activities and the Waste Calcining Facility (WCF). Deactivation activities primarily involve shutdown of operating systems and buildings, fissile and hazardous material removal, and related activities. A minimum required level of continued surveillance and maintenance is planned for each facility/process system to ensure necessary environmental, health, and safety margins are maintained and to support ongoing operations for ICPP facilities that are not being deactivated. Management of the ICPP was transferred from Westinghouse Idaho Nuclear Company, Inc. (WINCO) to Lockheed Idaho Technologies Company (LITCO) on October 1, 1994 as part of the INEL consolidated contract. This revision of the deactivation plan (formerly the Nuclear Fuel Reprocessing Phaseout Plan for the ICPP) is being published during the consolidation of the INEL site-wide contract and the information presented here is current as of October 31, 1994. LITCO has adopted the existing plans for the deactivation of ICPP reprocessing facilities and the plans developed under WINCO are still being actively pursued, although the change in management may result in changes which have not yet been identified. Accordingly, the contents of this plan are subject to revision.
Research Organization:
EG and G Idaho, Inc., Idaho Falls, ID (United States)
Sponsoring Organization:
USDOE, Washington, DC (United States)
DOE Contract Number:
AC07-94ID13223
OSTI ID:
137287
Report Number(s):
INEL--94/0165-Rev.1; ON: DE96002861
Country of Publication:
United States
Language:
English

Similar Records

Idaho Chemical Processing Plant and Plutonium-Uranium Extraction Plant phaseout/deactivation study
Technical Report · Fri Dec 31 23:00:00 EST 1993 · OSTI ID:10119366

Remote inspections at the Idaho National Engineering Laboratory
Conference · Tue Dec 31 23:00:00 EST 1991 · Transactions of the American Nuclear Society; (United States) · OSTI ID:7226618

HWMA closure plan for the Waste Calcining Facility at the Idaho National Engineering Laboratory
Technical Report · Wed May 01 00:00:00 EDT 1996 · OSTI ID:266635