Title: Insulation co-ordination aspects for power stations with generator circuit-breakers

Journal Article · · IEEE Transactions on Power Delivery
DOI:https://doi.org/10.1109/61.400920· OSTI ID:136572
 [1];  [2];  [3]
  1. ABB HV Technologies Ltd., Zuerich (Switzerland)
  2. Koeppl Power Experts, Lupfig (Switzerland)
  3. ABB Secheron Ltd., Geneva (Switzerland). Transformer Div.

The generator circuit-breaker (gen. c.b.) located between the generator and the step-up transformer, is now being applied world-wide. It has become a recognized electrical component of power stations which is largely due to economical advantages and increased power station availability. Technical protection considerations for power stations have always been the reason for discussion and the object of improvement. With the use of a gen. c.b., some points of view need to be considered anew. Not only the protection system in case of fault conditions will be influenced, but also the insulation co-ordination philosophy. Below the results of some calculations concerning expected overvoltages are presented. These calculations are based on a transformer rated 264/15.5kV, 220 MVA. But the results are transferable to other power plants. Some measurements carried out on a transformer of the same rating complement the calculations. The findings may contribute to an improvement in insulation co-ordination and protection of the electrical system generator--step-up transformer.

OSTI ID:
136572
Report Number(s):
CONF-940702-; ISSN 0885-8977; TRN: 96:000884
Journal Information:
IEEE Transactions on Power Delivery, Vol. 10, Issue 3; Conference: 1994 Institute of Electrical and Electronic Engineers/Power Engineering Society (IEEE/PES) summer meeting, San Francisco, CA (United States), 24-28 Jul 1994; Other Information: PBD: Jul 1995
Country of Publication:
United States