Parallel-in-time methods for power grid problems with generator and load ramping
Abstract
The objective of this technical memo is to describe the different methods that have been implemented and tested regarding the use of the MGRIT algorithm for generator and load ramping problems.
- Authors:
-
- Lawrence Livermore National Lab. (LLNL), Livermore, CA (United States)
- Publication Date:
- Research Org.:
- Lawrence Livermore National Lab. (LLNL), Livermore, CA (United States)
- Sponsoring Org.:
- USDOE
- OSTI Identifier:
- 1347676
- Report Number(s):
- LLNL-TR-726798
- DOE Contract Number:
- AC52-07NA27344
- Resource Type:
- Technical Report
- Country of Publication:
- United States
- Language:
- English
- Subject:
- 24 POWER TRANSMISSION AND DISTRIBUTION; 97 MATHEMATICS, COMPUTING, AND INFORMATION SCIENCE
Citation Formats
Lecouvez, Matthew. Parallel-in-time methods for power grid problems with generator and load ramping. United States: N. p., 2017.
Web. doi:10.2172/1347676.
Lecouvez, Matthew. Parallel-in-time methods for power grid problems with generator and load ramping. United States. https://doi.org/10.2172/1347676
Lecouvez, Matthew. Tue .
"Parallel-in-time methods for power grid problems with generator and load ramping". United States. https://doi.org/10.2172/1347676. https://www.osti.gov/servlets/purl/1347676.
@article{osti_1347676,
title = {Parallel-in-time methods for power grid problems with generator and load ramping},
author = {Lecouvez, Matthew},
abstractNote = {The objective of this technical memo is to describe the different methods that have been implemented and tested regarding the use of the MGRIT algorithm for generator and load ramping problems.},
doi = {10.2172/1347676},
url = {https://www.osti.gov/biblio/1347676},
journal = {},
number = ,
volume = ,
place = {United States},
year = {2017},
month = {1}
}
Save to My Library
You must Sign In or Create an Account in order to save documents to your library.