Revised restraint design to shorten steam generator replacement outage

Conference ·
OSTI ID:124708
 [1];  [2]
  1. Stone and Webster Engineering Corp., Boston, MA (United States). Mechanical Engineering Div.
  2. Virginia Power, Glen Allen, VA (United States). Steam Generator Replacement Project

The lessons learned from the North Anna Unit 1 steam generator replacement project and outage indicated that considerable time, money and material could be saved by designing and installing a revised upper restraint for the North Anna Unit 2 steam generator replacement. The existing Unit 2 steam generator upper restraint consisted of large weldments, splice and spacer plates, bolts and pins, and 144 shim plates. In order to minimize material and installation costs, a revised design for the upper restraint was developed that reduced the number of shim plates required.

OSTI ID:
124708
Report Number(s):
CONF-950740--; ISBN 0-7918-1332-0
Country of Publication:
United States
Language:
English

Similar Records

Steam-generator replacement sets new marks
Journal Article · Fri Mar 31 23:00:00 EST 1995 · Power (New York) · OSTI ID:55468

Split pin replacement at Surry Unit 1
Conference · Mon Dec 31 23:00:00 EST 1984 · Trans. Am. Nucl. Soc.; (United States) · OSTI ID:5146904

Maintain HCUs on-line, shorten refueling outages
Journal Article · Sun Sep 01 00:00:00 EDT 1996 · Power (New York) · OSTI ID:418010