FutureGen 2.0 Monitoring Program: An Overview of the Monitoring Approach and Technologies Selected for Implementation
Journal Article
·
· Energy Procedia
- Pacific Northwest National Laboratory (PNNL), Richland, WA (United States)
- Battelle Memorial Institute, Columbus, OH (United States)
The FutureGen 2.0 Project will design and build a first-of-its-kind, near-zero emissions coal-fueled power plant with carbon capture and storage (CCS). To assess storage site performance and meet the regulatory requirements of the Class VI Underground Injection Control (UIC) Program for CO2 Geologic Sequestration, the FutureGen 2.0 project will implement a suite of monitoring technologies designed to 1) evaluate CO2 mass balance and 2) detect any unforeseen loss in CO2 containment. The monitoring program will include direct monitoring of the injection stream and reservoir, and early-leak-detection monitoring directly above the primary confining zone. It will also implement an adaptive monitoring strategy whereby monitoring results are continually evaluated and the monitoring network is modified as required, including the option to drill additional wells in out-years. Wells will be monitored for changes in CO2 concentration and formation pressure, and other geochemical/isotopic signatures that provide indication of CO2 or brine leakage. Indirect geophysical monitoring technologies that were selected for implementation include passive seismic, integrated surface deformation, time-lapse gravity, and pulsed neutron capture logging. Near-surface monitoring approaches that have been initiated include surficial aquifer and surface- water monitoring, soil-gas monitoring, atmospheric monitoring, and hyperspectral data acquisition for assessment of vegetation conditions. Initially, only the collection of baseline data sets is planned; the need for additional near- surface monitoring will be continually evaluated throughout the design and operational phases of the project, and selected approaches may be reinstituted if conditions warrant. Given the current conceptual understanding of the subsurface environment, early and appreciable impacts to near-surface environments are not expected.
- Research Organization:
- Pacific Northwest National Laboratory (PNNL), Richland, WA (United States)
- Sponsoring Organization:
- USDOE
- Grant/Contract Number:
- AC05-76RL01830
- OSTI ID:
- 1209514
- Journal Information:
- Energy Procedia, Journal Name: Energy Procedia Journal Issue: C Vol. 63; ISSN 1876-6102
- Publisher:
- ElsevierCopyright Statement
- Country of Publication:
- United States
- Language:
- English
Similar Records
Geophysical Monitoring Methods Evaluation for the FutureGen 2.0 Project
Characterization and design of the FutureGen 2.0 carbon storage site
FutureGen 2.0 Monitoring Systems Design Basis and Technology Selection: Geohydrologic, Geochemical and Geophysical Considerations
Journal Article
·
Tue Dec 30 19:00:00 EST 2014
· Energy Procedia (Online)
·
OSTI ID:1209004
Characterization and design of the FutureGen 2.0 carbon storage site
Journal Article
·
Sat Oct 01 00:00:00 EDT 2016
· International Journal of Greenhouse Gas Control
·
OSTI ID:1322497
FutureGen 2.0 Monitoring Systems Design Basis and Technology Selection: Geohydrologic, Geochemical and Geophysical Considerations
Technical Report
·
Sat Nov 01 00:00:00 EDT 2014
·
OSTI ID:1986341