Development of Technologies and Capabilities for Coal Energy Resources
- Aerojet Rocketdyne, Canoga Park, CA (United States); Pratt & Whitney Rocketdyne, Incorporated
- Aerojet Rocketdyne, Canoga Park, CA (United States)
This is the final report for the Aerojet Rocketdyne (AR) Advanced Gasification Systems Development (AGSD) project that was initiated on October 1, 2004. The project’s primary objective is to demonstrate technologies that improve the availability and efficiency of gasification-based power plants and to reduce plant capital and operational costs. The objective will be accomplished by (1) development and testing of cooled refractory liners, (2) feed system development and demonstration, (3) pilot plant definition and planning, (4) transport gasifier feed analysis, (5) coal-biomass mixture feed analysis, and (6) coal-biomass mixture pilot scale tests. Task 1, development and testing of cooled refractory liners, was conducted at CANMET Energy Technology Centre in Ottawa, Canada. The test objectives were to screen high conductivity CMC materials with alternate manufacturing methods and a variety of surface treatments for cooled metal tubes in a slagging gasifier environment. During the CMC testing, it was found that a constantly cooled CMC will survive in good conditions and that high porosity CMC resulted in high material erosion and corrosion. During cooled tube testing, it was found that hard metal spray coat and bare Haynes 188 performed the best. Task 2, feed system development and demonstration, was conducted at at the Energy and Environmental Research Center (EERC) at the University of North Dakota (UND). For tasks 2.1-2.6, the test objective was to demonstrate 400-tons/day coal feed system operation (to 1,000 psia gasifier pressures) in ultra-dense phase flow without plugging and to achieve multi-element injector flow-split non-uniformities below 2 %RSD. Testing was successfully completed with no feed system plugging of the feed system. The majority of the other Task 2 activities were associated with the Dry Solids Pump design (Task 2.8 and 2.11), development (Task 2.10), fabrication (Task 2.12), amd testing (Task 2.13-2.15). A variety of tests were performed that verified the capability of the Dry Solids Pump to consolidate various pulverized feedstocks to a state capable of sealing and sustaining downstream outlet pressures during mechanical operation of the pump as well as during periods when the pump was turned off. However, the final operating goals were not achieved. Task 3, pilot plant definition and planning, was to define requirements for an advanced commercial gasifier with a cooled liner and to establish a preferred commercial gasifier system configuration to serve as the reference point for an advanced gasifier pilot plant concept definition. A pilot plant concept was successfully defined that is scalable and traceable to the commercial gasifier configuration. The schedule and cost for design, installation, and long-duration test operation of a pilot plant were estimated at 33 months and $$\$$$$25.6M. Taks 4, transport gasifier feed analysis, was to determine the effects of larger sized transport gasifier low rank coals within the AR dry solids pump. It was found for the two low-rank +100 mesh size transport gasifier coals that the cohesion of these larger materials was significantly less than the coals ground to minus 200 mesh. Also, the gas permeability of the MSL transport coal was found to be significantly higher than the permeability of the PRB transport coal. Task 5, coal-biomass mixture feed analysis, was to determine the effects of coal biomass blends within the AR ultra-dense phase feed system and dry solids pump, and to determine the cost of electricity increase of an integrated gasification combined cycle (IGCC) operating on coal/biomass blends with the AR dry solids pump and ultra-dense phase feed system. In summary, it was found that 75/25 wt% coal/corn stover blends produce reasonable economic results for IGCC operation with minimal dry solids pump modifications – especially if the coal is a low rank coal and the corn stover biomass is pelletized. The increase in electricity cost was found to be 1.1 cents/kWh. Task 6, coal-biomass mixture pilot scale tests, was to determine which coal/biomass blends could be tested in the current dry solids pump without major modifications. As reported in detail in the reports by Sprouse (2010) and Sprouse and Darby (2013), the coal/biomass blend having the least impact on pump configuration and operation is the 90/10 wt% Illinois #6 to corn stover ratio blend. The AGSD program was initiated on October 1, 2004. The interim final report was submitted on October 21, 2010 and covered Task 1, Task 2.1-2.9, and Task 3, performed during budget period 1. This final report covers Task 2.10-2.16, 4, 5, and 6, performed during budget period 2. The interim final report is attached as part of the appendix to this report.
- Research Organization:
- Aerojet Rocketdyne, Canoga Park, CA (United States)
- Sponsoring Organization:
- USDOE
- DOE Contract Number:
- FC26-04NT42237
- OSTI ID:
- 1136526
- Report Number(s):
- RD13--282
- Country of Publication:
- United States
- Language:
- English
Similar Records
CANMET Gasifier Liner Coupon Material Test Report
Advanced Gasifier Pilot Plant Concept Definition
CANMET Gasifier Liner Coupon Material Test Plan
Technical Report
·
Tue Jan 30 23:00:00 EST 2007
·
OSTI ID:921015
Advanced Gasifier Pilot Plant Concept Definition
Technical Report
·
Wed Aug 31 00:00:00 EDT 2005
·
OSTI ID:908748
CANMET Gasifier Liner Coupon Material Test Plan
Other
·
Sun Oct 30 00:00:00 EDT 2005
·
OSTI ID:891304