Test Report for Permanganate and Cold Strontium Strike for Tank 241-AN-102

Technical Report ·
DOI:https://doi.org/10.2172/1110194· OSTI ID:1110194
Tanks 241-AN-102 and 241-AN-107 supernatants contain soluble Sr-90 and transuranic elements that require removal prior to vitrification to comply with the Waste Treatment and Immobilization Plant immobilized low-activity waste specification (WTP Contract, DE-AC27-01RV 14136, Specification 2.2.2.8, "Radionuclide Concentration Limitations") and the U.S. Nuclear Regulatory Commission provisional agreement on waste incidental to reprocessing (letter, Paperiello, C. J., "Classification of Hanford Low-Activity Tank Waste Fraction"). These two tanks have high concentrations of organics and organic complexants and are referred to as complexant concentrate tanks. A precipitation process using sodium permanganate (NaMnO4) and strontium nitrate (Sr(NO3)2) was developed and tested with tank waste samples to precipitate Sr-90 and transuranic elements from the supernate (PNWD-3141, Optimization of Sr/TRU Removal Conditions with Samples of AN-102 Tank Waste). Testing documented in this report was conducted to further evaluate the use of the strontium nitrate/sodium permanganate process in tank farms with a retention time of up to 12 months. Previous testing was focused on developing a process for deployment in the ultrafiltration vessels in the Waste Treatment and Immobilization Plant. This environment is different from tank farms in two important ways: the waste is diluted in the Waste Treatment and Immobilization Plant to ~5.5 M sodium, whereas the supernate in the tank farms is ~9 M Na. Secondly, while the Waste Treatment and Immobilization Plant allows for a maximum treatment time of hours to days, the in-tank farms treatment of tanks 241-AN102 and 241-AN-107 will result in a retention time of months (perhaps up to12 months) before processing. A comparative compilation of separation processes for Sr/transuranics has been published as RPP-RPT-48340, Evaluation of Alternative Strontium and Transuranic Separation Processes. This report also listed the testing needs for the permanganate precipitation process to be field-deployable. A more comprehensive listing of future testing needs to allow the process to be field deployable are contained in RPP-PLAN-51288, Development Test Plan for Sr/TRU Precipitation Process.
Research Organization:
Hanford Site (HNF), Richland, WA (United States); USDOE Office of River Protection (ORP), Richland, WA (United States)
Sponsoring Organization:
USDOE Office of Environmental Management (EM)
Contributing Organization:
Washington River Protection Solutions
DOE Contract Number:
AC27-08RV14800
OSTI ID:
1110194
Report Number(s):
LAB-RPT--13-00008-Rev.0
Country of Publication:
United States
Language:
English

Similar Records

STRONTIUM & TRANSURANIC (TRU) SEPARATION PROCESS IN THE DOUBLE SHELL TANK (DST) SYSTEM
Technical Report · Fri Jun 10 00:00:00 EDT 2005 · OSTI ID:841017

Evaluation of Alternative Strontium and Transuranic Separation Processes
Technical Report · Thu Mar 31 20:00:00 EDT 2011 · OSTI ID:1047865

Investigation of Varied Strontium-Transuranic Precipitation Chemistries for Crossflow
Technical Report · Thu Jul 27 00:00:00 EDT 2000 · OSTI ID:759143