12 GeV Upgrade Project - Cryomodule Production

Conference ·
OSTI ID:1047819
The Thomas Jefferson National Accelerator Facility (Jefferson Lab) is producing ten 100+MV SRF cryomodules (C100) as part of the CEBAF 12 GeV Upgrade Project. Once installed, these cryomodules will become part of an integrated accelerator system upgrade that will result in doubling the energy of the CEBAF machine from 6 to 12 GeV. This paper will present a complete overview of the C100 cryomodule production process. The C100 cryomodule was designed to have the major components procured from private industry and assembled together at Jefferson Lab. In addition to measuring the integrated component performance, the performance of the individual components is verified prior to being released for production and assembly into a cryomodule. Following a comprehensive cold acceptance test of all subsystems, the completed C100 cryomodules are installed and commissioned in the CEBAF machine in preparation of accelerator operations. This overview of the cryomodule production process will include all principal performance measurements, acceptance criterion and up to date status of current activities.
Research Organization:
Thomas Jefferson National Accelerator Facility, Newport News, VA (United States)
Sponsoring Organization:
USDOE Office of Science (SC)
DOE Contract Number:
AC05-06OR23177
OSTI ID:
1047819
Report Number(s):
JLAB-ACC-12-1513; DOE/OR/23177-2258
Country of Publication:
United States
Language:
English

Similar Records

Overview and Lessons Learned of the Jefferson Lab Cryomodule Production for the CEBAF 12 GeV Upgrade
Conference · Sat Nov 30 23:00:00 EST 2013 · OSTI ID:1113734

CEBAF Upgrade: Cryomodule Performance And Lessons Learned
Conference · Fri Jan 31 23:00:00 EST 2014 · OSTI ID:1121254

Performance of First C100 Cryomodules for the CEBAF 12 GeV Upgrade Project
Conference · Sat Sep 01 00:00:00 EDT 2012 · OSTI ID:1088994