D-Zero Collider Detector CC Cooldown/Fill and Overview

Technical Report ·
DOI:https://doi.org/10.2172/1031816· OSTI ID:1031816
The cooldown will be immediately preceded by two trial pump downs; the insulating vacuum and the detector volume. The insulating vacuum must be established to a level below 10{sup -4} MM Hg to minimize the conduction heat load. The detector, aka cryostat, vacuum pump down must be able to reproduce the ultimate and rate-of-rise (ROR) values demonstrated in the clean room. It is anticipated, barring newly generated problems, it will take a few days to accomplish both of these tasks once the construction is complete, even though there has been incidental scavenger vacuum pumping. When the leak detectors are put away, the real Pump and Purge (P&P) begins.
Research Organization:
Fermi National Accelerator Laboratory (FNAL), Batavia, IL
Sponsoring Organization:
DOE Office of Science
DOE Contract Number:
AC02-07CH11359
OSTI ID:
1031816
Report Number(s):
FERMILAB-D0-EN-279
Country of Publication:
United States
Language:
English

Similar Records

CC Cryostat Cooldown Test Results
Technical Report · Fri Oct 16 00:00:00 EDT 1987 · OSTI ID:1030697

D-Zero Collider Detector CC Initial Vacuum Pumping Preparation and Procedure
Technical Report · Mon Apr 08 00:00:00 EDT 1991 · OSTI ID:1031808

D0 CC Cryostat Test Cooldown - Cooldown Time
Technical Report · Wed Aug 19 00:00:00 EDT 1987 · OSTI ID:1030712