Phase 2 Sampling Plan for Chestnut Ridge Operable Unit 2 (Filled Coal Ash Pond/Upper McCoy Branch) at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee. Environmental Restoration Program
Technical Report
·
OSTI ID:10181799
CDM Federal Programs Corporation (CDM Federal) was contracted by Martin Marietta Energy Systems, Inc. to prepare a Phase H Sampling Plan to describe field investigation work necessary to address regulatory agency review comments on the Remedial Investigation of Filled Coal Ash Pond (FCAP)/Upper McCoy Branch, Chestnut Ridge Operable Unit 2 at the Y-12 Plant, conducted by CH2M Hill in 1990. The scope and approach of the field investigation described in this plan specifically focus on deficiencies noted by the regulators in discussions at the comment resolution meeting of May 8, 1992, in Oak Ridge, Tennessee. This Phase II Sampling Plan includes a field sampling plan, a field and laboratory quality assurance project plan, a health and safety plan, a waste management plan, and appendixes providing an update to applicable or relevant and appropriate requirements for this site and field and laboratory testing methods and procedures. To address deficiencies noted by the regulators, the following activities will be conducted: Background surface soil and surface water/sediment samples will be collected based on statistical considerations for comparison to site data. Existing and new data to be collected will be used to support a human health risk assessment that includes the future homesteader scenario. Biological surveys, samples, and measurements will be collected/conducted to augment existing data and support an ecological risk assessment. Another round of groundwater sampling will be conducted, including on-site wells and the wells on Chestnut Ridge downgradient of the Security Pits. Borings will be completed in the FCAP to collect samples from below the surface depth to describe the chemical characteristics and volume of the ash. The volume of ash associated with sluice channel on Chestnut Ridge will be determined. Soil samples will be corrected below the coal ash in the FCAP and adjacent to sluice channel to evaluate soil contamination and migration of contaminants.
- Research Organization:
- Oak Ridge Y-12 Plant, TN (United States); CDM Federal Programs Corp., Oak Ridge, TN (United States)
- Sponsoring Organization:
- USDOE, Washington, DC (United States)
- DOE Contract Number:
- AC05-84OS21400
- OSTI ID:
- 10181799
- Report Number(s):
- DOE/OR--1054-D1; Y/ER--42-D1; ON: DE92041271
- Country of Publication:
- United States
- Language:
- English
Similar Records
Phase 2 Sampling Plan for Chestnut Ridge Operable Unit 2 (Filled Coal Ash Pond/Upper McCoy Branch) at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee
Phase 2 Sampling Plan for Chestnut Ridge Operable Unit 2 (Filled Coal Ash Pond/Upper McCoy Branch) at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee
Phase 2 Sampling Plan for Chestnut Ridge Operable Unit 2 (Filled Coal Ash Pond/Upper McCoy Branch) at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee. Environment Restoration Program
Technical Report
·
Sat Aug 01 00:00:00 EDT 1992
·
OSTI ID:7168368
Phase 2 Sampling Plan for Chestnut Ridge Operable Unit 2 (Filled Coal Ash Pond/Upper McCoy Branch) at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee
Technical Report
·
Thu Dec 31 23:00:00 EST 1992
·
OSTI ID:6509353
Phase 2 Sampling Plan for Chestnut Ridge Operable Unit 2 (Filled Coal Ash Pond/Upper McCoy Branch) at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee. Environment Restoration Program
Technical Report
·
Thu Dec 31 23:00:00 EST 1992
·
OSTI ID:10157178
Related Subjects
052002
12 MANAGEMENT OF RADIOACTIVE AND NON-RADIOACTIVE WASTES FROM NUCLEAR FACILITIES
54 ENVIRONMENTAL SCIENCES
540220
540230
540250
ASHES
CHEMICAL ANALYSIS
CHEMICALS MONITORING AND TRANSPORT
COAL
CONTAMINATION
GROUND WATER
HEALTH HAZARDS
HUMAN POPULATIONS
METALS
MONITORING
ORGANIC COMPOUNDS
PH VALUE
POLYCHLORINATED BIPHENYLS
POLYCYCLIC AROMATIC HYDROCARBONS
QUALITY ASSURANCE
RADIOACTIVE MATERIALS MONITORING AND TRANSPORT
RADIONUCLIDE MIGRATION
REMEDIAL ACTION
RISK ASSESSMENT
SAMPLING
SEDIMENTS
SETTLING PONDS
SITE RESOURCE AND USE STUDIES
SOILS
SURFACE WATERS
TOXICITY
URANIUM
WASTE DISPOSAL
WASTE DISPOSAL AND STORAGE
WASTE MANAGEMENT
Y-12 PLANT
12 MANAGEMENT OF RADIOACTIVE AND NON-RADIOACTIVE WASTES FROM NUCLEAR FACILITIES
54 ENVIRONMENTAL SCIENCES
540220
540230
540250
ASHES
CHEMICAL ANALYSIS
CHEMICALS MONITORING AND TRANSPORT
COAL
CONTAMINATION
GROUND WATER
HEALTH HAZARDS
HUMAN POPULATIONS
METALS
MONITORING
ORGANIC COMPOUNDS
PH VALUE
POLYCHLORINATED BIPHENYLS
POLYCYCLIC AROMATIC HYDROCARBONS
QUALITY ASSURANCE
RADIOACTIVE MATERIALS MONITORING AND TRANSPORT
RADIONUCLIDE MIGRATION
REMEDIAL ACTION
RISK ASSESSMENT
SAMPLING
SEDIMENTS
SETTLING PONDS
SITE RESOURCE AND USE STUDIES
SOILS
SURFACE WATERS
TOXICITY
URANIUM
WASTE DISPOSAL
WASTE DISPOSAL AND STORAGE
WASTE MANAGEMENT
Y-12 PLANT