Cost update: Technology, safety, and costs of decommissioning a reference uranium fuel fabrication plant

Technical Report ·
DOI:https://doi.org/10.2172/10167747· OSTI ID:10167747

The cost estimates originally developed in NUREG/CR-1266 for commissioning a reference low-enrichment uranium fuel fabrication plant are updated from 1978 to early 1993 dollars. During this time, the costs for labor and materials increased approximately at the rate of inflation, the cost of energy increased more slowly than the rate of inflation, and the cost of low-level radioactive waste disposal increased much more rapidly than the rate of inflation. The results of the analysis indicate that the estimated costs for the immediate dismantlement and decontamination for unrestricted facility release (DECON) of the reference plant have increased from the mid-1978 value of $3.57 million to $8.08 million in 1993 with in-compact low-level radioactive waste disposal at the US Ecoloay facility near Richland, Washington. The cost estimate rises to $19.62 million with out-of-compact radioactive waste disposal at the Chem-Nuclear facility near Barnwell, South Carolina. A methodology and a formula are presented for estimating the cost of decommissioning the reference uranium fuel fabrication plant at some future time, based on these early 1993 cost estimates. The formula contains essentially the same elements as the formula given in 10 CFR 50.75 for escalating the decommissioning costs for nuclear power reactors to some future time.

Research Organization:
Pacific Northwest Lab., Richland, WA (United States)
Sponsoring Organization:
USDOE, Washington, DC (United States)
DOE Contract Number:
AC06-76RL01830
OSTI ID:
10167747
Report Number(s):
PNL--9965; ON: DE94015285
Country of Publication:
United States
Language:
English