York County Energy Partners CFB Cogeneration Project. Annual report, [September 30, 1992--September 30, 1993]
The Department of Energy, under the Clean Coal Technology program, proposes to provide cost-shared financial assistance for the construction of a utility-scale circulating fluidized bed technology cogeneration facility by York County Energy Partners, L.P (YCEP). YCEP, a project company of ir Products and Chemicals, Inc., would design, construct and operate a 250 megawatt (gross) coal-fired cogeneration facility on a 38-acre parcel in North Codorus Township, York County, Pennsylvania. The facility would be located adjacent to the P. H. Glatfelter Company paper mill, the proposed steam host. Electricity would be delivered to Metropolitan Edison Company. The facility would demonstrate new technology designed to greatly increase energy efficiency and reduce air pollutant emissions over current generally available commercial technology which utilizes coal fuel. The facility would include a single train circulating fluidized bed boiler, a pollution control train consisting of limestone injection for reducing emissions of sulfur dioxide by greater than 92 percent, selective non-catalytic reduction for reducing emissions of nitrogen oxides, and a fabric filter (baghouse) for reducing emissions of particulates. Section II of this report provides a general description of the facility. Section III describes the site specifics associated with the facility when it was proposed to be located in West Manchester Township. After the Cooperative Agreement was signed, YCEP decided to move the proposed site to North Codorus Township. The reasons for the move and the site specifics of that site are detailed in Section IV. This section of the report also provides detailed descriptions of several key pieces of equipment. The circulating fluidized bed boiler (CFB), its design scale-up and testing is given particular emphasis.
- Research Organization:
- York County Energy Partners, L.P., Allentown, PA (United States)
- Sponsoring Organization:
- USDOE, Washington, DC (United States)
- DOE Contract Number:
- FC21-91MC27403
- OSTI ID:
- 10161273
- Report Number(s):
- DOE/MC/27403--3754; ON: DE94004128; BR: AZ0185000
- Country of Publication:
- United States
- Language:
- English
Similar Records
Design considerations for a 250 MWe CFB
York County Energy Partners DOE CCI ACFB demonstration project
York County Energy Partners DOE CCI ACFB demonstration project
Conference
·
Sat Dec 30 23:00:00 EST 1995
·
OSTI ID:287929
York County Energy Partners DOE CCI ACFB demonstration project
Conference
·
Tue Sep 01 00:00:00 EDT 1992
·
OSTI ID:10179814
York County Energy Partners DOE CCI ACFB demonstration project
Conference
·
Tue Dec 31 23:00:00 EST 1991
·
OSTI ID:7249570
Related Subjects
01 COAL, LIGNITE, AND PEAT
010800
014000
20 FOSSIL-FUELED POWER PLANTS
200104
200202
AIR POLLUTION CONTROL
COAL
COGENERATION
COMBUSTION
COMPONENTS
DESIGN
EXPERIMENTAL DATA
FILTERS
FLOWSHEETS
FLUE GAS
FLUIDIZED BED BOILERS
FLUIDIZED-BED COMBUSTION
FOSSIL-FUEL POWER PLANTS
LIMESTONE
NITROGEN OXIDES
NOXIOUS GAS AND PARTICULATE EMISSIONS
PARTICULATES
PENNSYLVANIA
PERFORMANCE TESTING
PROGRESS REPORT
SULFUR DIOXIDE
WASTE MANAGEMENT
010800
014000
20 FOSSIL-FUELED POWER PLANTS
200104
200202
AIR POLLUTION CONTROL
COAL
COGENERATION
COMBUSTION
COMPONENTS
DESIGN
EXPERIMENTAL DATA
FILTERS
FLOWSHEETS
FLUE GAS
FLUIDIZED BED BOILERS
FLUIDIZED-BED COMBUSTION
FOSSIL-FUEL POWER PLANTS
LIMESTONE
NITROGEN OXIDES
NOXIOUS GAS AND PARTICULATE EMISSIONS
PARTICULATES
PENNSYLVANIA
PERFORMANCE TESTING
PROGRESS REPORT
SULFUR DIOXIDE
WASTE MANAGEMENT