TWRS privatization phase 1 electrical power system

Technical Report ·
DOI:https://doi.org/10.2172/10154232· OSTI ID:10154232
This document includes Conceptual Design Report (CDR) for a new 11 km (7 miles) 230 kV transmission line and a new 40 MVA substation (A6) which will be located east of Grout Facility in 200E Area tank farm. This substation will provide electrical power up to 20 MW each for two private contractor facilities for immobilization and disposal of low activity waste (LAW).
Research Organization:
Fluor Daniel Hanford Inc., Richland, WA (United States)
Sponsoring Organization:
USDOE Office of Environmental Restoration and Waste Management, Washington, DC (United States)
DOE Contract Number:
AC06-96RL13200
OSTI ID:
10154232
Report Number(s):
HNF-SD-W503-CDR--001; ON: DE99051063; BR: EW3130010