Basis for design scope: Plutonium Reclamation Facility, Z Plant, Project CAC-880
This report discuss the design of the Plutonium Reclamation Facility the capacity of which will be 300 kilograms per month or 3600 kilograms per year or plutonium. The subject facility, as the name implies, must be extremely flexible in its ability to handle a wide variety of feed materials. The new facility will be operating on a three-shift day, five-day week, 40-week year with an overall efficiency of 75 percent; twelve weeks per year will be required for ``turnaround`` time to enable campaign operation for segregation of feed plutonium by isotopic content.
- Research Organization:
- General Electric Co., Richland, WA (United States). Hanford Atomic Products Operation
- Sponsoring Organization:
- USDOE, Washington, DC (United States)
- DOE Contract Number:
- AC06-76RL01830
- OSTI ID:
- 10145488
- Report Number(s):
- HW--64941; ON: DE94010530
- Country of Publication:
- United States
- Language:
- English
Similar Records
Design Scope of the Z Plant Plutonium Reclamation Facility: Project CAC-880
SHIELDING REQUIREMENTS FOR NPR PRODUCTION IN PLUTONIUM RECLAMATION FACILITY- PROJECT CAC-880
GAMMA SHIELDING CALCULATIONS FOR SLAG AND CRUCIBLE FRAGMENT HANDLING- PLUTONIUM RECLAMATION FACILITY, PROJECT CAC-880
Technical Report
·
Mon Oct 17 00:00:00 EDT 1960
·
OSTI ID:10123932
SHIELDING REQUIREMENTS FOR NPR PRODUCTION IN PLUTONIUM RECLAMATION FACILITY- PROJECT CAC-880
Technical Report
·
Sat Dec 31 23:00:00 EST 1960
·
OSTI ID:4819081
GAMMA SHIELDING CALCULATIONS FOR SLAG AND CRUCIBLE FRAGMENT HANDLING- PLUTONIUM RECLAMATION FACILITY, PROJECT CAC-880
Technical Report
·
Tue Sep 27 00:00:00 EDT 1960
·
OSTI ID:4843897