skip to main content
OSTI.GOV title logo U.S. Department of Energy
Office of Scientific and Technical Information

Title: Pilot-Scale Testing of an Integrated Circuit for the Extraction of Rare Earth Minerals and Elements from Coal and Coal Byproducts Using Advanced Separation Technologies

Other ·
OSTI ID:1798663

The primary objective of this project was to develop and demonstrate an integrated pilot-scale circuitry for recovering high-value rare earth elements (REEs) from coal and coal byproducts. The target performance was to produce a mixed REE product with content of at least two percent by weight on a dry mass basis in a cost-effective and environmentally benign manner. During the first nine months of the project period (Phase 2 Budget Period 2), pilot plant construction was completed including all field site startup activities such as permitting, engineering design, procurement/bidding, unit fabrication, site construction, equipment installation, module assembly, safety training, and circuit shakedown. During the remaining 21 months of project period (Phase 2 Budget Period 3), detailed field-testing activities were performed including feedstock sample collection and preparation, exploratory testing, circuit modification, detailed parametric study, and performance optimization. A detailed techno-economic analysis was performed based on the pilot plant testing findings which provided various scenarios for REE production. The project successfully accomplished the proposed target performance by producing mixed rare earth oxide (REO) with greater than 90% purity by weight in a continuous pilot scale operation from two distinctly different coarse refuse materials (i.e., West Kentucky No. 13 and Fire Clay coal seams), and at least three secondary sources (i.e., heap leach process and naturally formed acid mine drainage system). Project partners included the University of Kentucky, Virginia Tech, West Virginia University, Alliance Coal, Blackhawk Mining, Mineral Refining Company, and Mineral Separation Technologies. The pilot scale test facility was constructed at a former mining complex owned by Alliance Natural Resource Partners (Alliance Coal). The site was rehabilitated to accommodate the equipment installation, construction and fabrication, electrical power requirement, water line management and containment. The process units constructed and installed included X-ray sorting unit, crushing and grinding unit, physical separation unit, acid leaching unit, solvent extraction unit, and wastewater management unit. A rare earth mineral concentration unit was constructed as a standalone unit for flexible operation. A detailed environmental assessment and control plan was carried out to identify and quantify any potential impacts of the pilot-scale processing circuitry on the human and eco-system health and well-being. Corresponding mitigation strategies and control measures were provided. A conceptual flowsheet was developed to effectively remove thorium and uranium from high purity rare earth oxide mix or any potential radionuclide enriched stream. The two distinct feedstock materials were secured from the Blackhawk Mining Complex in eastern Kentucky where the Fire Clay (Hazard No. 4) seam is processed. The West Kentucky No. 13 (Baker) coarse refuse material was collected from an active process stream at an Alliance coal preparation plant located in western Kentucky. Characterization analysis indicated that both of feed materials generated from the two sources contained >300 ppm of TREEs on a dry whole mass basis which met the requirements for a qualified feed stock. The two feedstocks were further upgraded using a dual x-ray sorter to prepare the feed material for hydrometallurgical circuit. Thermal treatment on feed material prior to leaching was found to: 1) improve the leaching recovery of REEs, 2) increase the leaching kinetics, and 3) allow the leaching reaction to occur at lower acidity. Roasting at 600°C was selected as the pre-treatment condition for both West Kentucky No. 13 and Fire Clay coarse refuse material. Over 40% of leaching recovery was achieved by roasting West Kentucky No. 13 material having a top particle size of 3 mm in the pilot scale operation using 1.2M sulfuric acid leaching at 75OC. Initial pilot scale testing involved continuous operation of the pilot plant for 94 hours. The leaching unit was operated at solid-to-liquid ratio of 1 to 10 (w/v) using 0.5M sulfuric acid solution at a temperature of 75°C. The continuous solvent extraction circuit utilized rougher and cleaner units with DEHPA and TBP as the extractants. An innovative stripping circuit was developed to accumulate the REE concentration in the stripping solution to a level above 600 ppm. A bleed stream from the recycled strip solution was treated using oxalic acid precipitation which produced a high grade rare earth oxalate. The oxalate product was roasted to remove the oxalate which produced a rare earth oxide product having a purity greater 90%. Due to high concentrations of contaminant ions in the pregnant leach solution (PLS), a modified flowsheet was developed that involved pre-concentration of the REEs using multiple stages of precipitation and redissolution. The advantage of this process was improved removal of contamination before the downstream purification process and a significant cost reduction relative to the circuit that utilized the solvent extraction process. The modified circuitry included processes involving leaching, multistage precipitation, redissolution, and oxalate precipitation followed by roasting of the oxalate product. The circuit produced a mixed REO that was 92.96% pure from the initial test. A detailed parametric test plan was carried out which involved varying key parameters including solids feed rate, acid flowrate, acid concentration, multistage precipitation pH, redissolution pH, oxalate precipitation dosage and pH. The response variables included REE recovery, contaminant recovery, REO product grade and overall chemical consumption. Test results indicated that the acid-to-solid ratio is the key parameter to leaching efficiency as performance deteriorated with an increase in solids concentration. The optimal pH determined for REE precipitation and redissolution was 6.5 and 2.5, respectively. Additional tests were conducted to further improve the flowsheet. Recirculating a portion of the PLS to the feed of the leach tanks improved the leaching performance by lowering the pH of the leaching system and reducing the contamination recovery by shortening the residence time. Moreover, the removal of Al prior to REE precipitation significantly reduced the oxalic acid consumption in the oxalate precipitation circuit. The modified circuit produced over 90% grade REO by weight from both West Kentucky No. 13 and Fire Clay coarse refuse material in pilot scale continuous test programs. A case analysis model was developed to project the REE and major contaminants concentration in each PLS stream based on the leaching condition, pH cut point, and oxalic acid dosage. A correlation was established using empirical and semi-empirical models. Using the models, chemical consumption required for each stage was predicted based on the projected performance of the hydrometallurgy circuit. After identifying the optimum conditions, validation tests were carried out for the treatment of both West Kentucky No. 13 and Fire Clay coarse refuse materials in the pilot plant. The actual circuit performance and chemical consumptions were very close to the model predictions. Other than the two coarse refuse sources, several secondary feedstocks were also tested in the pilot plant facility. A “heap leach” system was constructed using the coarse refuse material generated from cleaning the West Kentucky No. 13 seam coal. Using the two stage SX rougher and cleaner circuit, a concentrate with a grade >90% REO was produced while recovering >97% of the REEs from the heap leach PLS. Naturally generated acid mine drainage (AMD) from West Kentucky No.13 mine was processed using the multistage precipitation circuit in the pilot plant in a test conducted for a period of 32 hours. The final grade of the mix RE oxide produced from the AMD was 90.84% with an overall circuit recovery of 64%. The primary source of REE was the selective precipitation steps involving iron and aluminum rejection. The hydrophobic-hydrophilic separation (HHS) process was proven to effectively recover coal from fine waste materials. For REM recovery, the HHS process was able to produce concentrates at grades of approximately 1.8% REE on an ash basis; however, recovery values were typically low, <10%, under the optimal conditions determined in the laboratory-scale testing. Staged testing of the pilot-scale HHS process for coal recovery and semi-continuous laboratory testing for REM testing showed that a total concentration ratio of more than 15x was observed for the REM recovery process. A circuit simulation package was developed for REE extraction and purification using a spreadsheet-based platform (Microsoft Excel). The REESim circuit simulation package is configured to track the mass and volume flows of components passing through a series of unit operations specified and configured by the user. The mass rates can then be utilized by the user to determine important performance indicators such as product mass yields, concentrate purity levels, element-by-element recoveries, and so forth. The techno-economic analysis showed that the roasting and leaching operations were the most expensive capital items, each contributing approximately 30% to the total capital cost. One notable contributor to the high production costs was the low REE recovery observed in the pilot scale trials. The product basket price was shown to have a strong influence on the economic viability of the scenarios, with the scandium price being the most significant influencer. Operating cost was shown to be extremely sensitive to REE recovery, REE feed grade, and leaching acid consumption. An analysis of ten different scenarios for a 500 t/h commercial operation revealed that three were economically favorable, producing internal rates of return varying from 27.7% to 33.1% and payback periods of 4 to 5 years. The project successfully developed and demonstrated a process to recover REEs from coal and coal byproducts in a pilot-plant operation which consistently produced over 90% grade REO mix from varies types of feedstocks. Commercialization analysis showed that the technology readiness level successfully achieved TRL 6 at the end of the project and demonstrated the need and the potential for scaling the process to further advance the technologies toward the goal of providing a domestic supply of REEs at a commercial scale.

Research Organization:
Univ. of Kentucky, Lexington, KY (United States)
Sponsoring Organization:
USDOE Office of Fossil Energy (FE)
Contributing Organization:
Alliance Coal, Mineral Refining Corporation, Kentucky River Properties, Mineral Separation Technologies, Blackhawk Mining
DOE Contract Number:
FE0027035
OSTI ID:
1798663
Report Number(s):
DOE-UKY-0463
Country of Publication:
United States
Language:
English