skip to main content
OSTI.GOV title logo U.S. Department of Energy
Office of Scientific and Technical Information

Title: Materials for Advanced Ultra-Supercritical (AUSC) Steam Turbines – AUSC Component Demonstration

Other ·
OSTI ID:1485813
 [1];  [2];  [2];  [2];  [1];  [3];  [4]
  1. Energy Industries of Ohio
  2. Electric Power Research Institute
  3. AECOM
  4. Hendrix Engineering Solutions, Inc.

The work by the United States Department of Energy (U.S. DOE)/Ohio Coal Development Office (OCDO) Advanced Ultra-Supercritical (AUSC) Steam Boiler and Turbine Materials Consortia from 2001 through September 2015 was primarily focused on lab scale and pilot scale materials testing. The field testing included air-cooled probes and steam-cooled “loops” that were installed into existing utility boilers to gain exposure of these materials to realistic conditions of high temperature and corrosion due to the constituents in the coal ash. Successful research and development resulted in identification of metallic alloy materials and fabrication processes suited for power generation applications with metal temperatures up to approximately 1472°F (800°C). These materials or alloys have shown, in extensive laboratory tests and shop fabrication studies, to have excellent applicability for high-efficiency low CO2 transformational power generation technologies. However, as valuable as these material field tests have been for obtaining information, their scale is significantly below that required to minimize the risk associated with a power company building a multi-billion-dollar AUSC power plant. To decrease the identified risk barriers to full-scale implementation of these advanced materials, the U.S. DOE/OCDO AUSC Steam Boiler and Turbine Materials Consortia identified the key areas of the technology that need to be tested at a larger scale. Based upon the recommendations and outcome of a Consortia-sponsored workshop with the U.S.’s leading utilities, a Component Test (ComTest) Program for AUSC was proposed. The AUSC ComTest program would define materials performance requirements, plan for overall advanced system integration, design critical component tests, fabricate components for testing from advanced materials, and carry out the tests. A Pre-FEED evaluation of the test facility including the evaluation of three potential sites has been completed and previously reported. This report describes the Front-End Engineering Design (FEED), Detailed Engineering and the Environmental Assessment of the ComTest project. A significant amount of work was accomplished during Phase 1 to identity the components, as well as the component size, that would be manufactured from advanced alloys such as INCONEL 740H or HAYNES 282 alloys. Pathways to supply these components for ComTest have been identified as well as any further development that would be required. Every project of this nature has challenges and this project was no exception. The greatest challenge has been the project cost. Largely due to the infrastructure and balance of plant equipment upgrades required for Youngstown Thermal, the estimated project cost for the “base case” project was greater than originally budgeted. The project team spent a significant amount of time exploring opportunities for reducing the project cost. These options included: • Youngstown Thermal was exploring building a Combined Heat and Power (CHP) unit at their facility. The Youngstown Thermal staff, supported by Thermal Engineering Group, worked with the project team to determine whether it was economically desirable to supply ComTest with steam and other utilities, which would be supplied by the CHP project. • The project team also evaluated opportunities to optimize the project scope to reduce cost, such as reducing project scope by eliminating the Superheater Outlet Header test. • Southern Company had offered two sites as possible host locations for ComTest. Both sites had infrastructure in place such as steam from an existing unit, natural gas, cooling water and ample electrical power that would be required to be added at the Youngstown Thermal site. Utilizing this existing infrastructure could reduce the project cost. An additional project challenge was the departure of Babcock and Wilcox from the project in September 2016. This project setback was overcome by GE Power’s willingness to assume the design of the ComTest superheater. Since the project could not proceed without the superheater, this was a very positive project development. The merger of the GE Power and Alstom Power steam turbine divisions created synergies leading to the conclusion that instead of building a small-scale turbine, a more practical and useful endeavor would be to validate the manufacturing technology and supplier readiness for fabricating and machining full scale steam turbine components. Consequently, in March 2017, GE Power decided that a steam turbine test would not be necessary as part of the ComTest demonstration. Removing the operational testing of the steam turbine from ComTest further reduced the total project cost. Additionally, there was an opportunity to move ComTest from Youngstown Thermal to one of the Southern Company sites and operate ComTest at supercritical steam conditions and test the steam turbine main stop/control valve at a temperature and pressure that would be representative of the conditions of a high pressure steam turbine inlet valve. The steam could also possibly be returned to the host boiler so there would be no economic penalty of using this steam for ComTest. Relocating the project could further reduce the project cost due to the infrastructure already in place, including high pressure natural gas and cooling water, and the potential for heat integration, allowing a reduction of operating costs. Due to these potential cost reductions, it was decided to move the project away from Youngstown Thermal in March 2017. As integrating ComTest at the Southern Company site was explored, an issue was raised regarding the integration of the ComTest cycle with the plant steam cycle. Steam would be supplied to ComTest at nominally ~3865 psia and 775°F. The steam would be heated with natural gas to 1400°F for the valve test and then cooled to 1000°F so that the steam would be returned to the host boiler at the same conditions as their high pressure steam turbine inlet. However, there were concerns raised that the addition of the energy (natural gas) to the steam could trigger a New Source Review on the unit. Southern Company did not want ComTest to cause this review, so condensing all of the steam exiting ComTest and returning it to the host steam cycle as condensate was explored to insure there would be no implication that ComTest was adding energy to the host plant’s steam cycle. Ultimately, Southern Company decided that they wanted to “decouple” ComTest from the operating unit, making ComTest self-supporting, similar to the Youngstown Thermal “base case.” Without the steam turbine, the project team reached a consensus that operating the ComTest Superheater and steam turbine valves at the typical pressure of a package boiler (~1000 psig) would not generate enough useful technical information to justify the cost of the test. Therefore, it was decided in the December 2017 project quarterly meeting to cancel the operational phase of ComTest. Throughout the engineering phase of ComTest, manufacturing and supply chain challenges were identified. When GE Power recommended dropping the steam turbine test from ComTest, they identified many important manufacturing issues that should be evaluated and demonstrated. Other challenges had been raised by the GE Power group designing the superheater as well as those engineering components such as pressure relief and steam turbine bypass valves. In the December 2017 meeting, the project team decided that it was more beneficial to the AUSC technology to pursue these manufacturing and supply chain issues as Phase 2 of the ComTest project. This report is organized in the following manner: • Section 2 discusses the ComTest project background and organization. • Section 3 discussed project management. • Section 4 discusses the design of the ComTest AUSC components – the Superheater, steam turbine and Superheater Outlet Header. • Section 5 discusses the implementation of ComTest at Youngstown Thermal and the Southern Company site. • Section 6 discusses the development of the AUSC Supply Chain • Section 7 discusses the recommended plan for Phase 2 of ComTest

Research Organization:
ENERGY INDUSTRIES OF OHIO
Sponsoring Organization:
USDOE
Contributing Organization:
Energy Industries of Ohio; Electric Power Research Institute; GE Power; The Babcock and Wilcox Company; AECOM
DOE Contract Number:
FE0025064
OSTI ID:
1485813
Report Number(s):
DOE-EIO-EPRI-0025064; OER-CDO-D-15-01
Country of Publication:
United States
Language:
English