skip to main content
OSTI.GOV title logo U.S. Department of Energy
Office of Scientific and Technical Information

Title: Grande Ronde Endemic Spring Chinook Salmon Supplementation Program; Satellite Facilities Operation and Maintenance, 2005 Annual Report.

Technical Report ·
DOI:https://doi.org/10.2172/900558· OSTI ID:900558
; ;  [1]
  1. Confederated Tribes of the Umatilla Indian Reservation, Department of Natural Resources, Pendleton, OR

There were 2 acclimation periods at the Catherine Creek Acclimation Facility (CCAF) in 2005. During the early acclimation period, 130,748 smolts were delivered from Lookingglass Hatchery (LGH) on 7 March. This group contained progeny of both the captive (53%) and conventional broodstock programs. The size of the fish at delivery was 23.9 fish/lb. Volitional releases began 14 March 2005 and ended 27 March with an estimated total (based on PIT tag detections of 3,187) of 29,402 fish leaving the raceways. This was 22.5% of the total fish delivered. Fish remaining in the raceways after volitional release were forced out. Hourly detections of PIT-tagged fish showed that most of the fish left around 1900 hours. The size of the fish just before the volitional release was 23.9 and the size of the fish remaining just before the forced release was 23.2 fish/lb. The total mortality for the acclimation period was 204 (0.16%). The total number of fish released from the acclimation facility during the early period was 130,544. During the second acclimation period 59,100 smolts were delivered from LGH on 28 March. This group was comprised entirely of progeny from the conventional broodstock program. The size of the fish at delivery was 21.8 fish/lb. Volitional releases began 3 April 2005 and ended with a force out emergency release on 7 April. The size of the fish just before the volitional release was 21.8. The total mortality for the acclimation period was 64 (0.11 %). The total number of fish released from the acclimation facility during the late period was 59,036. There was only 1 planned acclimation period at the Upper Grande Ronde Acclimation Facility (UGRAF) in 2005. During the early acclimation period 105,418 smolts were delivered from LGH on 8 March. This group was comprised entirely of progeny from the conventional broodstock program. The size of the fish at delivery was 21.0 fish/lb. There was no volitional release in 2005 due to freezing air and water conditions prompting an early release. The total mortality for the acclimation period was 49 (0.05 %). The total number of fish released from the acclimation facility during the late period was 105,369. Maintenance and repair activities were conducted at the acclimation facilities in 2005. Facility maintenance work consisted of snow removal, installation of drainage lines, removal of gravel from intake area, installation of new gate at the CCAF, and complete overhaul of 2 travel trailers. The Catherine Creek Adult Capture Facility (CCACF) was put into operation on 11 February 2005. The first adult summer steelhead was captured on 4 March. A total of 190 adult summer steelhead were trapped and released from 4 March to 16 May 2005. Peak arrival at the trap was the week of 8 April. The first adult spring Chinook salmon was captured at CCACF on 6 May 2005. A total of 226 spring Chinook salmon were trapped from 6 May to 8 July 2005. There were 56 adults and 4 jacks unmarked and 136 adult and 30 jack marked spring Chinook salmon trapped. Peak arrival at the trap was the week of 10 June for the unmarked and marked fish. None of the captive broodstock returns were collected for broodstock. Broodstock was collected systematically over the entire return from 31 May to 6 July 2005. Ten of the 34 broodstock collected and transported from CCACF to LGH were unmarked fish trapped. About 18% of the naturally produced adult males and females trapped were taken to LGH for broodstock. One jack was collected for every 5 adult males that were taken to LGH. A total of 30 age 4 and 5 and 4 age 3 fish were transported to LGH for broodstock. The hatchery component of the broodstock was 66.7%. Five weekly spawning surveys were conducted below the weir on Catherine Creek beginning 30 June 2005. During these surveys no live or dead fish were observed. The trap was removed from Catherine Creek on 3 August 2005. Temperatures at the CCACF ranged from -0.1 C on 14 February to 23.7 C on 21 July. The hourly temperatures at the adult trap during the period of operation showed that the lowest water temperatures usually occurred around 0700 hours and the highest water temperatures usually occurred around 1600 hours. Facility maintenance work at CCACF consisted of construction of a debris barrier in front of the intake, maintenance of weir, and weed abatement. The Upper Grande Ronde Adult Collection Facility (UGRACF) was put into operation on 10 March 2005. The first adult summer steelhead was captured on 8 April. A total of 41 adult summer steelhead were trapped and released from 8 April to 11 May 2005. Peak arrival at the trap was the week of 22 April. The first adult spring Chinook salmon was captured at UGRACF on 31 May 2005. A total of 277 spring Chinook salmon were trapped from 31 May to 3 August 2005. There were 14 adults and no jacks unmarked and 257 adult and 6 jack marked spring Chinook salmon trapped. Peak arrival at the trap for both unmarked and marked fish was 10 June.

Research Organization:
Confederated Tribes of the Umatilla Indian Reservation, Department of Natural Resources
Sponsoring Organization:
United States. Bonneville Power Administration.
DOE Contract Number:
00006509
OSTI ID:
900558
Report Number(s):
DOE/BP-00006509-8; R&D Project: 199800703; TRN: US200711%%702
Country of Publication:
United States
Language:
English