Vestibule and Cask Preparation Mechanical Handling Calculation
The scope of this document is to develop the size, operational envelopes, and major requirements of the equipment to be used in the vestibule, cask preparation area, and the crane maintenance area of the Fuel Handling Facility. This calculation is intended to support the License Application (LA) submittal of December 2004, in accordance with the directive given by DOE correspondence received on the 27th of January 2004 entitled: ''Authorization for Bechtel SAIC Company L.L.C. to Include a Bare Fuel Handling Facility and Increased Aging Capacity in the License Application, Contract Number DE-AC28-01R W12101'' (Ref. 167124). This correspondence was appended by further correspondence received on the 19th of February 2004 entitled: ''Technical Direction to Bechtel SAIC Company L.L. C. for Surface Facility Improvements, Contract Number DE-AC28-01R W12101; TDL No. 04-024'' (Ref. 16875 1). These documents give the authorization for a Fuel Handling Facility to be included in the baseline. The limitations of this preliminary calculation lie within the assumptions of section 5 , as this calculation is part of an evolutionary design process.
- Research Organization:
- YMP (Yucca Mountain Project, Las Vegas, Nevada)
- Sponsoring Organization:
- USDOE
- DOE Contract Number:
- NA
- OSTI ID:
- 850427
- Report Number(s):
- 210-00C-FH00-00100-000-00A REV 00A; ENG.20040601.0023, DC#41430; TRN: US0600413
- Country of Publication:
- United States
- Language:
- English
Similar Records
Canister Handling Facility Criticality Safety Calculations
Transportation Cask Receipt/Return Facility Criticality Safety Evaluations