As-Built Verification Plan Spent Nuclear Fuel Canister Storage Building MCO Handling Machine
This as-built verification plan outlines the methodology and responsibilities that will be implemented during the as-built field verification activity for the Canister Storage Building (CSB) MCO HANDLING MACHINE (MHM). This as-built verification plan covers THE ELECTRICAL PORTION of the CONSTRUCTION PERFORMED BY POWER CITY UNDER CONTRACT TO MOWAT. The as-built verifications will be performed in accordance Administrative Procedure AP 6-012-00, Spent Nuclear Fuel Project As-Built Verification Plan Development Process, revision I. The results of the verification walkdown will be documented in a verification walkdown completion package, approved by the Design Authority (DA), and maintained in the CSB project files.
- Research Organization:
- Fluor Hanford, Richland, WA (United States)
- Sponsoring Organization:
- USDOE Office of Environmental Management (EM) (US)
- DOE Contract Number:
- AC06-96RL13200
- OSTI ID:
- 805641
- Report Number(s):
- SNF-6448, Rev.1; ECN-654499; TRN: US0301229
- Resource Relation:
- Other Information: PBD: 19 Oct 2000
- Country of Publication:
- United States
- Language:
- English