Project Design Concept Primary Ventilation System
Tank Farm Restoration and Safe Operation (TFRSO), Project W-3 14 was established to provide upgrades that would improve the reliability and extend the system life of portions of the waste transfer, electrical, ventilation, instrumentation and control systems for the Hanford Site Tank Farms. An assessment of the tank farm system was conducted and the results are documented in system assessment reports. Based on the deficiencies identified in the tank farm system assessment reports, and additional requirements analysis performed in support of the River Protection Project (RPP), an approved scope for the TFRSO effort was developed and documented in the Upgrade Scope Summary Report (USSR), WHC-SD-W314-RPT-003, Rev. 4. The USSR establishes the need for the upgrades and identifies the specific equipment to be addressed by this project. This Project Design Concept (PDC) is in support of the Phase 2 upgrades and provides an overall description of the operations concept for the W-314 Primary Ventilation Systems. Actual specifications, test requirements, and procedures are not included in this PDC. The PDC is a ''living'' document, which will be updated throughout the design development process to provide a progressively more detailed description of the W-314 Primary Ventilation Systems design. The Phase 2 upgrades to the Primary Ventilation Systems shall ensure that the applicable current requirements are met for: Regulatory Compliance; Safety; Mission Requirements; Reliability; and Operational Requirements.
- Research Organization:
- NHC (US)
- Sponsoring Organization:
- USDOE Office of Environmental Management (EM) (US)
- DOE Contract Number:
- AC27-99RL14047
- OSTI ID:
- 805372
- Report Number(s):
- RPP-6066, Rev.0; EDT-630776; TRN: US0301297
- Resource Relation:
- Other Information: PBD: 2 Oct 2000
- Country of Publication:
- United States
- Language:
- English
Similar Records
Design review report: AN valve pit upgrades for Project W-314, tank farm restoration and safe operations