Title: Corrective Action Plan for Corrective Action Unit 240: Area 25 Vehicle Washdown Nevada Test Site, Nevada

Technical Report ·
DOI:https://doi.org/10.2172/783904· OSTI ID:783904

The purpose of this Corrective Action Plan is to provide the strategy and methodology to close the Area 25 Vehicle Washdown. The CAU will be closed following state and federal regulations and the FFACO (1996). Site characterization was performed during March 1999 at each CAS. Soil samples were collected at each CAS using a direct-push method. Soil samples were collected from the surface to depths of up to 2.7 m (9 ft) below ground surface. In addition, the gravel sump at CAS 25-07-02 (F and J Roads Pad) was sampled using a backhoe. Soil samples were collected from depths of 0 to 0.6 m (0 to 2 ft) below the gravel layer in the sump.

Research Organization:
Bechtel Nevada Corp. (US)
Sponsoring Organization:
US Department of Energy (US)
DOE Contract Number:
AC08-96NV11718
OSTI ID:
783904
Report Number(s):
DOE/NV-611; DOE/NV/11718-400; TRN: AH200128%%295
Resource Relation:
Other Information: PBD: 1 May 2000
Country of Publication:
United States
Language:
English