Design review report for the SY-101 RAPID mitigation system
This report documents design reviews conducted of the SY-101 Respond And Pump In Days (RAPID) Mitigation System. As part of the SY-101 Surface-Level-Rise Remediation Project, the SY-101 WID Mitigation System will reduce the potential unacceptable consequences of crust growth in Tank 241-SY-101 (SY-101). Projections of the crust growth rate indicate that the waste level in the tank may reach the juncture of the primary and secondary confinement structures of the tank late in 1999. Because of this time constraint, many design activities are being conducted in parallel and design reviews were conducted for system adequacy as well as design implementation throughout the process. Design implementation, as used in this design review report, is the final component selection (e.g., which circuit breaker, valve, or thermocouple) that meets the approved design requirements, system design, and design and procurement specifications. Design implementation includes the necessary analysis, testing, verification, and qualification to demonstrate compliance with the system design and design requirements. Design implementation is outside the scope of this design review. The design activities performed prior to detailed design implementation (i.e., system mission requirements, functional design requirements, technical criteria, system conceptual design, and where design and build contracts were placed, the procurement specification) have been reviewed and are within the scope of this design review report. Detailed design implementation will be controlled, reviewed, and where appropriate, approved in accordance with Tank Waste Remediation System (TWRS) engineering procedures. Review of detailed design implementation will continue until all components necessary to perform the transfer function are installed and tested.
- Research Organization:
- Hanford Site (HNF), Richland, WA (United States)
- Sponsoring Organization:
- US DOE Office of Environmental Management (US)
- DOE Contract Number:
- AC06-96RL13200
- OSTI ID:
- 782334
- Report Number(s):
- HNF-4519-REV0; TRN: US0203144
- Resource Relation:
- Other Information: PBD: 24 May 1999
- Country of Publication:
- United States
- Language:
- English
Similar Records
Process Control Plan for Tank 241-SY-101 Surface Level Rise Remediation
Hazard evaluation for transfer of waste from tank 241-SY-101 to tank 241-SY-102