Title: Project Execution Plan Project 98L-EWW-460 Plutonium Stabilization and Handling DOE 98-D-453

Technical Report ·
DOI:https://doi.org/10.2172/803927· OSTI ID:803927

This Project Execution Plan (PEP) describes the management methods and responsibilities of the project participants. Project W-460 is sufficiently large to warrant a stand alone PEP. This project specific PEP describes the relationships and responsibilities of the project team and identifies the technical, schedule, and cost baselines that have been established for the project. The Department of Energy (DOE), Hanford Works (Hanford), at Richland, Wa. currently does not have a system capable of stabilizing or packaging large quantities of plutonium-bearing solids to meet DOE technical standard DOE-STD-3013-99. This project will allow Hanford to meet this standard by installing stabilization and packaging equipment (SPE). The SPE is capable of stabilizing and packaging the current inventory of greater than 30 percent plutonium-bearing materials currently stored in the Plutonium Finishing Plant's (PFP) vaults into 3013 storage containers. The scope of this project is to procure and install the SPE via a Hanford contract and coordination with the Savannah River Site. In addition, the project will modify PFP vaults and upgrade the PFP Laboratory measurement systems. The Facility infrastructure will be modified to support the new SPE system and the new standardized storage container configuration.

Research Organization:
Fluor Hanford, Richland, WA (United States)
Sponsoring Organization:
USDOE Office of Environmental Management (EM) (US)
DOE Contract Number:
AC06-96RL13200
OSTI ID:
803927
Report Number(s):
HNF-4681, Rev.1; EDT-629651; TRN: US0300729
Resource Relation:
Other Information: PBD: 21 Jun 2000