Title: Phase 2 Rebaseline Report for Tank Farm Restoration and Safe Operations Project W-314

Technical Report ·
DOI:https://doi.org/10.2172/801850· OSTI ID:801850

Project W-314, (97-D-402) Tank Farm Restoration and Safe Operations is a multi-year, multiphase project established to upgrade selected 200 East and West Area Tank Farms to support the long-term mission of waste storage, retrieval, and transfer for vitrification. Key drivers for these upgrades include the planned timetable for transfer of waste to the privatized vitrification facility, regulatory compliance requirements (i.e., Washington State and Federal Regulations), and the Tri-Party Agreement (TPA). The previous baseline scope for Project W-314 was established based upon tank farm system assessments performed five to six years ago and was reflected in the previous baseline cost estimate, the Accelerated Replanning Estimate, completed in July 1997. The Accelerated Replanning Estimate splits the project into two phases: Phase 1 provides upgrades necessary to assure reliable waste retrieval and transfer to the anticipated vitrification plant. Phase 2 provides upgrades to selected primary and annulus tank farm ventilation systems that are required for compliant waste transfer, as well as other compliance-based upgrades to existing River Protection Project (WP) facilities and systems. The Accelerated Replanning Estimate provided the basis for Baseline Change Request TWR 97-066, which identified Phases 1 and 2 as $95 million and $206.5 million, respectively. Following completion of the Accelerated Replanning Estimate, several changes occurred that prompted a decision to rebaseline Phase 1, and subsequently Phase 2. Paramount among these was the delay in the Privatization schedule (90% case), lessons learned (in the year since the Accelerated Planning Report had been completed), and the adoption of an alternate waste transfer system route. The rebaselined cost of phase 1, $157 million, was substantially higher than the Accelerated Replanning Estimate for a number of reasons more thoroughly discussed in the Phase 1 Rebaseline Report, HNF-3781, January 1999. Since the July 1997 Accelerated Replanning Estimate there have also been changes to the tank farm authorization basis and Programmatic needs. For example, Tank Farm Operations has been installing new Continuous Air Monitors (CAMS) and liquid level measuring devices in order to achieve desired monitoring improvements years earlier than provided by Phase 2. In summary, the decision to rebaseline Phase 2 was prompted by: (1) the shifting of selected Phase 2 scope to Phase 1 during the Phase 1 rebaselining, (2) changes in the authorization basis, (3) programmatic needs, and (4) the dated nature of the existing scope definition. Figure 1.1 presents a summary of the key changes born the previous baseline and their collective impact on the cost of Phase 2.

Research Organization:
CH2M Hill Hanford Group, Inc., Richland, WA (United States)
Sponsoring Organization:
ENVIRONMENTAL MANAGEMENT (US)
DOE Contract Number:
AC06-96RL13200
OSTI ID:
801850
Report Number(s):
HNF-5109, Rev.0; EDT-626448; TRN: US0300537
Resource Relation:
Other Information: PBD: 27 Mar 2000