Title: Piezometer completion report for borehole cluster sites DC-19, DC-20, and DC-22

Technical Report ·
OSTI ID:5449982

This report describes the design and installation of multi-level piezometers at borehole cluster sites DC-19, DC-20 and DC-22. The network of borehole cluster sites will provide facilities for multi-level water-level monitoring across the RRL for piezometer baseline monitoring and for large-scale hydraulic stress testing. These groundwater-monitoring facilities were installed between August 1983 and March 1984. Three series of piezometer nests (A-, C- and D-series) were installed in nine hydrogeologic units (monitoring horizons) within the Columbia River Basalt Group at each borehole cluster site. In addition to the piezometer facilities, a B-series pumping well was installed at borehole cluster sites DC-20 and DC-22. The A-series piezometer nest monitors the basal Ringold sediments and the Rattlesnake Ridge interbed. The C-series piezometer nests monitors the six deepest horizons, which are in increasing depth, the Priest Rapids interflow, Sentinel Gap flow top, Ginkgo flow top, Rocky Coulee flow top, Cohassett flow top and Umtanum flow top. The D-series piezometer monitors the Mabton interbed. The B-series pumping well was completed in the Priest Rapids interflow. 21 refs., 6 figs., 6 tabs.

Research Organization:
Rockwell International Corp., Richland, WA (USA). Rockwell Hanford Operations
Sponsoring Organization:
DOE/RW
DOE Contract Number:
AC06-77RL01030
OSTI ID:
5449982
Report Number(s):
RHO-BWI-TI-226-Rev.1; ON: TI90003469
Country of Publication:
United States
Language:
English