Title: An Effective Earned Value Management System (EVMS) is a Team Sport

Journal Article · · Project Management Journal
ORCiD logo [1];  [2];  [3]; ORCiD logo [2]
  1. Department of Civil Engineering and Construction Management, California State University, Northridge, CA, USA
  2. School of Sustainable Engineering and the Built Environment, Arizona State University, Tempe, AZ, USA
  3. National Center of Excellence on SMART Innovations, School of Sustainable Engineering and the Built Environment, Arizona State University, Tempe, AZ, USA

We present a novel framework to assess 27 earned value management system (EVMS) environment factors and investigate their impact on project performance. A study of the EVMS literature, a survey of practitioners, and focus group meetings with 36 EVMS industry and government experts, supported the development of the framework. Focus groups involving 80 practitioners refined and tested it. We analyzed performance data from 35 completed projects/programs representing over US$21.8 billion in total cost; a project demonstrating a positive environment could save up to 25% in cost versus baseline. Practitioners can develop an effective EVMS environment by following the provided guidance.

Sponsoring Organization:
USDOE
OSTI ID:
2305752
Journal Information:
Project Management Journal, Journal Name: Project Management Journal Journal Issue: 4 Vol. 55; ISSN 8756-9728
Publisher:
SAGE PublicationsCopyright Statement
Country of Publication:
Country unknown/Code not available
Language:
English

References (53)

The Mediating Role of Project Citizenship Behavior in the Relationship Between Organizational Justice Dimensions and Project Success journal July 2021
Causal Inferences on the Cost Overruns and Schedule Delays of Large-Scale U.S. Federal Defense and Intelligence Acquisition Programs journal March 2010
Demonstrating the Impact and Benefits of CMMI (Trademark): An Update and Preliminary Results report October 2003
Impacts of Change Orders on Cost and Schedule Performance and the Correlation with Project Size of DB Building Projects journal August 2019
Project maturity in organisations journal August 2003
Conditions of success for earned value analysis in projects journal April 2018
Putting the technical back into socio-technical systems research journal June 2007
A Review on Key Performance Indicators for Measuring Real Estate Project Success journal August 2021
Novel Earned Value Management System Maturity Framework and Its Relation to Project Performance journal June 2023
Sham project compliance behaviour journal November 2019
The Costs and Benefits of the Earned Value Management Process journal November 1998
United states department of defense (DoD) real property repair, alterations, maintenance, and construction project contract data: 2009–2020. journal October 2020
Construction delays causing risks on time and cost - a critical review journal February 2012
Project Complexity Indicators and Management Strategies – A Delphi Study journal January 2016
EVMS Environment Assessment Tool Development Process text January 2022
Impact of Measuring Operational-Level Planning Reliability on Management-Level Project Performance journal September 2015
Techniques for determining importance: Balancing scientific method and subjectivity journal June 2007
The relative importance of project success dimensions journal April 1997
A model for effective implementation of Earned Value Management methodology journal July 2003
A socio‐technical systems approach to cell design: case study and analysis journal December 1998
Forward-Looking State-of-the-Art Review on Earned Value Management Systems: The Disconnect between Academia and Industry journal May 2022
A comparison of the performance of various project control methods using earned value management systems journal April 2015
Earned Value Analysis, Implementation Barriers, and Maturity Level in oil & gas Production journal December 2019
The Charrette HANDBOOK book October 2017
Qualitative Analysis for Social Scientists journal January 2010
Quantitative Analysis of the Impacts of Out-of-Sequence Work on Project Performance journal August 2020
Quantifying FEED Maturity and Its Impact on Project Performance in Large Industrial Projects journal September 2019
Project Management Journal® Special Issue on Project Behavior journal November 2021
The Project Manager's Leadership Style as a Success Factor on Projects: A Literature Review journal June 2005
Using Historical NASA Cost and Schedule Growth to Set Future Program and Project Reserve Guidelines conference January 2007
A new framework for determining critical success/failure factors in projects journal June 1996
Critical Success Factors Affecting Project Performance: An Analysis of Tools, Practices, and Managerial Support journal April 2019
Improving the practical application of the Delphi method in group-based judgment: A six-step prescription for a well-founded and defensible process journal October 2019
The Role of Project Management Maturity and Organizational Culture in Perceived Performance journal September 2009
Earned Value Management System State of Practice: Identifying Critical Subprocesses, Challenges, and Environment Factors of a High-Performing EVMS journal July 2021
Improving project forecast accuracy by integrating earned value management with exponential smoothing and reference class forecasting journal January 2017
Allocation and Management of Cost Contingency in Projects journal November 2016
Learning to learn, from past to future journal April 2002
Management of multi-method engineering design research: a case study journal June 2002
The efficacy of SMARTER — Simple Multi-Attribute Rating Technique Extended to Ranking journal September 1996
Toward a Unified Validation Framework in Mixed Methods Research journal October 2007
Employing Technology to Enable Remote Research Charrettes as a Method for Engaging Industry and Uncovering Best Practices: A Novel Approach for a Post-COVID-19 World journal November 2022
Exchange and Power in Social Life book September 2017
A framework for international quality management research: Development and validation of a measurement instrument journal September 1999
Earned Value Management System (EVMS) Reliability: A Review of Existing EVMS Literature conference November 2020
Socio‐technical systems theory: an intervention strategy for organizational development journal August 1997
Defining the Success Status of Construction Projects Based on Quantitative Performance Metrics Thresholds journal March 2023
A proposed framework of sustainable self-evaluation maturity within companies: an exploratory study journal June 2016
How Power Influences Behavior in Projects: A Theory of Planned Behavior Perspective journal December 2021
Cost Performance Index Stability: Fact or Fiction? journal April 1992
Handbook of Parametric and Nonparametric Statistical Procedures book August 2003
Predictability Index: Novel Metric to Assess Cost and Schedule Performance journal December 2015
Which is the correct statistical test to use? journal January 2008