Fermilab's Horizontal Test Stand Upgrade Overview and Commissioning
- Fermi National Accelerator Laboratory (FNAL), Batavia, IL (United States)
Cryo-assemblies with the Nb3 Sn MQXFA low-beta quadrupoles for the High Luminosity LHC (HL-LHC) upgrade will be tested at Fermilab's magnet test facility. A total of 10 cryo-assemblies will be delivered to CERN within the US HL-LHC Accelerator Upgrade Project (AUP). The horizontal test stand at Fermilab already has been used for testing the existing LHC inner-triplet quadrupoles, but the stand and corresponding electrical and cryogenic sub-systems were not operational for more than a decade. In order to restore the test stand functions and meet the design and test requirements for the HL-LHC magnets, the existing horizontal test facility at Fermilab underwent a significant refurbishment of the cryogenic and mechanical components. Most of the upgrades were completed and verified during so called zero-magnet test by late 2020, and then final commissioning of the upgraded horizontal test stand was completed during the first cryo-assembly test in 2023. These tests verified the major cryo-mechanical installations, as well as the basic test stand operations, including controlled cooldown and operation at 1.9 K, magnet protection and process controls. Here, in this paper, overview of the Fermilab's horizontal test facility upgrade and commissioning of these upgrades are presented.
- Research Organization:
- Fermi National Accelerator Laboratory (FNAL), Batavia, IL (United States)
- Sponsoring Organization:
- USDOE Office of Science (SC), High Energy Physics (HEP)
- Grant/Contract Number:
- AC02-07CH11359
- OSTI ID:
- 2283703
- Report Number(s):
- FERMILAB-CONF-23-474-TD; oai:inspirehep.net:2747080; TRN: US2408858
- Journal Information:
- IEEE Transactions on Applied Superconductivity, Vol. 34, Issue 5; ISSN 1051-8223
- Publisher:
- IEEECopyright Statement
- Country of Publication:
- United States
- Language:
- English
Similar Records
Test Stand Functional Requirements for Testing MQXFA Magnets and Q1/Q3 Cryostat Assemblies (Rev.3)
Magnetic Measurements and Alignment Results of LQXFA/B Cold Mass Assemblies at Fermilab