Title:
INTERIM REPORT, PRODUCTION TEST 105-522-E -- EXAMINATION OF PILE PROCESS TUBES REMOVED FROM 100-C AND 100-DR PILES
Subject Terms:
100 AreasC ReactorDR ReactorHANFORD PRODUCTION REACTORSMetallurgyPT-105-522-EReactor TechnologyTUBE CORROSION
Document Location:
DOE Public Reading Room - Hanford Battelle P.O. Box 999 MS H2-53 Richland WA 99352 (509)372-7443
Publication Date:
1956 Mar 06
Declassification Date:
1981 Jul 13
Declassification Status:
Declassified
Accession Number:
RL-1-363388
Document Number(s):
HW-41795
Originating Research Org.:
GE - HAPO
OpenNet Entry Date:
2004 Feb 24
OpenNet Modified Date:
2015 Aug 10
Description/Abstract:
GIVES RESULTS OF THE EXAMINATION OF 18 C PILE PROCESS TUBES AND 12 DR PILE PROCESS TUBES. EXCEPT FOR LEAKER TUBE 3163DR, NO SEVERE INTERNAL CORROSION HAS TAKEN PLACE IN THOSE TUBES EXAMINED. LIGHT TO MEDIUM CORROSION WAS OBSERVED ON THE OUTSIDE OF SOME OF THE TUBES. FILM PATCHES WERE FOUND IN A NUMBER OF TUBES.